Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR11-00496 INSP-Sprinkler Rough-in/Hydro5/22/20125/22/20125/22/2012 5:10:51 PMPPART
Parking garage dry system work completed.
FIR11-00604 FIR-Aging Inspection5/22/20125/22/20125/22/2012 4:26:10 PM PEND
Need inspection request for work completed and permit final.
BLD12-00635 FIRE-Conference5/22/20125/22/20125/22/2012 4:23:41 PMADONE
Fire alarm permit FIR12-00234 currently under review. This FACP replacement work will enable system interconnection for supervision of the hood suppression system per IFC requirements as needed.
BLD12-00730 FIRE-Final Inspection5/22/20125/22/20125/22/2012 4:18:44 PMPPART
Racking final is contingent upon project related fire alarm work per permit documents.
BLD12-00508 FIRE-Final Inspection5/22/20125/22/20125/22/2012 4:14:03 PMPNR
Please call prior to arrival -- Tony Phone #: ###-#### * Discussed with contractor project related fire alarm permit work (FIR12-00146) must be completed, inspected and finaled prior to building fire life safety approvals. Finals to be rescheduled as agreed.
BLD12-00955 FIRE-Sprinkler Rough-in5/22/20125/22/20125/22/2012 4:02:04 PMAPART
Project related fire sprinkler work okayed for cover.
BLD12-00406 FIRE-Final Inspection5/22/20125/22/20125/22/2012 11:07:39 AMAPASS
Fire life safety finaled.
BLD12-00532 FIRE-Final Inspection5/18/20125/22/20125/22/2012 11:07:03 AMAPASS
Fire life safety approved pending doors and hardware at the back room and restroom are installed prior to structural final as discussed. Remainder of inspection items passed.