Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD02-00697 BLD-Final5/22/20025/23/20025/23/2002 12:00:00 AMANR
MIKE ###-####
BLD02-01146 BLD-Foundation5/22/20025/23/20025/23/2002 12:00:00 AMAPART
###-#### work in progress rebar is in 90% of form work complete no one on site 5/23/2002 10:43:16 AM
BLD02-00227 BLD-Final5/22/20025/23/20025/23/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 05/22/2002 at 14:09:44. Contact: ###-####.energy code items 5/23/2002 10:42:10 AM
BLD02-00130 BLD-Footing5/21/20025/23/20025/23/2002 12:00:00 AMAPASS
DAVE ###-#### needs to have property line up or some thing so walls can be checked 5/23/2002 10:45:51 AM
BLD02-01154 BLD-Footing5/22/20025/23/20025/23/2002 12:00:00 AMPPART
###-#### basement footings ok to pour 5/23/2002 3:19:48 PM
BLD01-03154 BLD-Final5/22/20025/23/20025/23/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 05/22/2002 at 16:36:31. Contact: ###-####.
BLD02-01248 BLD-Foundation5/23/20025/23/20025/23/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 05/23/2002 at 11:15:57. Contact: ###-####.
BLD02-00995 BLD-Framing/Rough-in5/23/20025/23/20025/23/2002 12:00:00 AMPPASS
Scheduled by Inspector: 425 On 5/23/2002 11:30:48 AM fix on roof over hang 5/23/2002 3:41:51 PM
BLD02-01119 BLD-Footing5/23/20025/23/20025/23/2002 12:00:00 AMPPART
Scheduled by Inspector: 425 On 5/23/2002 12:23:18 PM