PLM05-01698
| Plumbing Rough-in | 5/24/2005 | 5/24/2005 | 5/24/2005 3:09:17 PM | P | FAIL |
|
|
###-#### - steve nail plate 1/2 bath lav waste none of the phone numbers would work.
|
PLM05-01697
| Plumbing Rough-in | 5/24/2005 | 5/24/2005 | 5/24/2005 3:06:07 PM | P | FAIL |
|
|
###-#### - steve pex with in 12" of recessed light fixture.
|
PLM05-01496
| Plumbing Rough-in | 5/23/2005 | 5/24/2005 | 5/24/2005 2:10:58 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Alderson ri ok
|
PLM05-01700
| Water and/or Sewer | 5/24/2005 | 5/24/2005 | 5/24/2005 1:53:15 PM | P | PASS |
|
|
WILL BE READY FOR INSPECTION AT 1:00PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska sw final ok
|
PLM05-01701
| Water and/or Sewer | 5/24/2005 | 5/24/2005 | 5/24/2005 1:52:51 PM | P | PASS |
|
|
WILL BE READY FOR INSPECTION AT 1:00 PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska sw final ok
|
PLM05-01673
| Plumbing Rough-in | 5/24/2005 | 5/24/2005 | 5/24/2005 1:33:13 PM | P | PASS |
|
|
ri ok
|
PLM04-02979
| Final | 5/24/2005 | 5/24/2005 | 5/24/2005 11:50:36 AM | P | PASS |
|
|
call 1/2 1st before insp - mark; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie final ok
|
PLM05-01695
| Water and/or Sewer | 5/24/2005 | 5/24/2005 | 5/24/2005 11:29:55 AM | P | PART |
|
|
Ready Now; Phone #: ###-#### Internet Inspection Request from: Dave Wood will call when they find the existing stub, their out about 16' from the building.
|
PLM05-01696
| Water and/or Sewer | 5/24/2005 | 5/24/2005 | 5/24/2005 11:27:09 AM | P | PART |
|
|
Ready Now; Phone #: ###-#### Internet Inspection Request from: Dave Wood will call when they find the existing sewer stub
|
PLM05-00417
| Final | 5/24/2005 | 5/24/2005 | 5/24/2005 10:58:09 AM | P | PASS |
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--call 1st before insp final ok
|
PLM05-01693
| Plumbing Rough-in | 5/23/2005 | 5/24/2005 | 5/24/2005 10:31:24 AM | A | PASS |
|
|
###-#### dan ri ok with 1 1/2" service connection in crawlspace capped and nail plates installed.
|
PLM03-01438
| Plumbing Rough-in | 5/24/2005 | 5/24/2005 | 5/24/2005 9:41:51 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/24/2005 at 6:40:32 AM. Contact: ###-####. ri complete washer area
|
PLM05-01690
| Plumbing Rough-in | 5/23/2005 | 5/24/2005 | 5/24/2005 9:10:37 AM | A | PASS |
|
|
michael - ###-#### Note: water heater and laundry drain reset existing water heater final ok
|
PLM05-01638
| Groundwork | 5/20/2005 | 5/24/2005 | 5/24/2005 8:44:54 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/20/2005 at 1:22:44 PM. Contact: ###-####. gw ok
|
PLM05-01696
| DOC - Permit Finaled | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
oops this ones is ok tied to new stub final ok
|
PLM05-01696
| DOC - Permit Finaled | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
oops this ones is ok tied to new stub final ok
|
PLM05-01690
| Final | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
|
PLM05-01671
| DOC - Permit Finaled | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
|
PLM05-00895
| Final | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 5/24/2005 at 8:30:30 AM. Contact: ###-####.///cancelled per jill 5/24/05 12:50pm LEM
|
PLM05-01700
| DOC - Permit Finaled | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
WILL BE READY FOR INSPECTION AT 1:00PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska
|
PLM05-01701
| DOC - Permit Finaled | 5/24/2005 | 5/24/2005 | 5/24/2005 12:00:00 AM | P | PASS |
|
|
WILL BE READY FOR INSPECTION AT 1:00 PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska
|