Inspections for the day of: Tuesday, May 24, 2011.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC11-01493 Final5/19/20115/24/20115/24/2011 4:53:39 PMPPASS
late afternoon please. Phone #: ###-#### >> Inspection requested via web by PAM SCHANK
MEC11-01524 Final5/23/20115/24/20115/24/2011 3:49:45 PMPPASS
Mid to late afternoon. Thanks!! Phone #: ###-#### >> Inspection requested via web by April Sims
MEC11-01520 Final5/23/20115/24/20115/24/2011 2:35:16 PMPPASS
Please do in the PM, please do rough and final any questions contact Jason ###-#### or chad Phone #: ###-#### >> Inspection requested via web by Diane Myslivy
MEC11-00950 Final5/24/20115/24/20115/24/2011 2:26:55 PMPPASS
oleg Phone #: ###-####
MEC11-01274 Final5/24/20115/24/20115/24/2011 2:07:25 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Dustin Rich
MEC11-01274 Pressure Test5/24/20115/24/20115/24/2011 2:07:11 PMPPASS
20# pressure test ok
MEC11-01274 Rough-in5/24/20115/24/20115/24/2011 2:06:30 PMPPASS
hvac as per wrightsoft,no duct blaster test yet,look for this on final
ESC10-00012 Aging Inspection5/24/20115/24/20115/24/2011 1:18:57 PM PASS
project still under construction
PLM11-00906 Groundwork5/24/20115/24/20115/24/2011 1:05:48 PMPPASS
PLM11-00907 Groundwork5/23/20115/24/20115/24/2011 1:05:33 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Kristy Watson
PLM11-00756 Water and/or Sewer5/24/20115/24/20115/24/2011 12:36:37 PMACANC
The owner wants to have the work that we have done finaled for Temporary Occupancy . We are still working out other detials of the Job, the owner wants to get the final work approved by the inspector. Please leave this permit open for additional add on to scope of work. Phone #: ###-#### >> Inspection requested via web by Joseph Corcoran
PLM11-00756 Final5/24/20115/24/20115/24/2011 12:36:16 PMAPASS
PLM11-00906 Groundwork5/23/20115/24/20115/24/2011 11:38:46 AMACANC
Phone #: ###-#### >> Inspection requested via web by Kristy Watson reschedule for PM inspection
PLM11-00861 Final5/23/20115/24/20115/24/2011 10:42:00 AMAPASS
thank you Phone #: ###-#### >> Inspection requested via web by Aaron Johns
PLM11-00240 Final5/23/20115/24/20115/24/2011 10:16:10 AMAPASS
martin Phone #: ###-####
ESC10-00621 DOC - Permit Finaled5/24/20115/24/20115/24/2011 8:10:13 AMPPASS
PLM11-00907 Water and/or Sewer5/23/20115/24/20115/23/2011 7:29:09 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Kristy Watson Inspection cancelled from web by: Kristy Watson