Inspections for the day of: Wednesday, May 25, 2011.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR11-00166 INSP-Final Inspection5/25/20115/25/20115/25/2011 4:31:30 PMPCANC
Cancelled due to time constraints. Rescheduled for tomorrow.
BLD11-00532 FIRE-Final Inspection5/24/20115/25/20115/25/2011 4:03:36 PMPFAIL
No cooking is allowed until approved by Ron Amandus: ###-####, provide permit for the hood suppression system changes, provide permit for the new facp DACT that was installed, repair the rear exit discharge light.
FIR11-00195 INSP-Sprinkler Rough-in/Hydro5/24/20115/25/20115/25/2011 3:12:40 PMPPART
The overhead hydro and sprinkler rough-in passed. The plans are approved for max. storage height of 15'. The current storage height is 17' and solid shelving with 2x4 supports are being utilized. So the storage arrangement needs to be permanantly modified or resubmittals are required. Also the project can not be finaled until a racking permit is applied for.
FIR11-00095 INSP-Sprinkler Rough-in5/24/20115/25/20115/25/2011 2:08:15 PMPPASS
Underground supply piping cover passed. Piping can be covered.
FIR11-00181 INSP-Sprinkler Rough-in/Hydro5/24/20115/25/20115/25/2011 1:47:47 PMAPASS
Hydro test of the wet and dry system passed.
FIR11-00166 INSP-Final Inspection5/24/20115/25/20115/25/2011 8:18:53 AMAFAIL
Jeremy is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus.


Left message with Melodie at office I was on the way. Contractor not on site. Shipping clips were still on heads and second piece of the canopies is missing as well.