FIR11-00166
| INSP-Final Inspection | 5/25/2011 | 5/25/2011 | 5/25/2011 4:31:30 PM | P | CANC |
|
|
Cancelled due to time constraints. Rescheduled for tomorrow.
|
BLD11-00532
| FIRE-Final Inspection | 5/24/2011 | 5/25/2011 | 5/25/2011 4:03:36 PM | P | FAIL |
|
|
No cooking is allowed until approved by Ron Amandus: ###-####, provide permit for the hood suppression system changes, provide permit for the new facp DACT that was installed, repair the rear exit discharge light.
|
FIR11-00195
| INSP-Sprinkler Rough-in/Hydro | 5/24/2011 | 5/25/2011 | 5/25/2011 3:12:40 PM | P | PART |
|
|
The overhead hydro and sprinkler rough-in passed. The plans are approved for max. storage height of 15'. The current storage height is 17' and solid shelving with 2x4 supports are being utilized. So the storage arrangement needs to be permanantly modified or resubmittals are required. Also the project can not be finaled until a racking permit is applied for.
|
FIR11-00095
| INSP-Sprinkler Rough-in | 5/24/2011 | 5/25/2011 | 5/25/2011 2:08:15 PM | P | PASS |
|
|
Underground supply piping cover passed. Piping can be covered.
|
FIR11-00181
| INSP-Sprinkler Rough-in/Hydro | 5/24/2011 | 5/25/2011 | 5/25/2011 1:47:47 PM | A | PASS |
|
|
Hydro test of the wet and dry system passed.
|
FIR11-00166
| INSP-Final Inspection | 5/24/2011 | 5/25/2011 | 5/25/2011 8:18:53 AM | A | FAIL |
|
|
Jeremy is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus.
Left message with Melodie at office I was on the way. Contractor not on site. Shipping clips were still on heads and second piece of the canopies is missing as well.
|