BLD12-00951
| FIRE-Final Inspection | 5/25/2012 | 5/25/2012 | 5/25/2012 3:56:16 PM | P | PASS |
|
|
life safety passed
|
BLD12-01009
| FIRE-Final Inspection | 5/25/2012 | 5/25/2012 | 5/25/2012 3:25:21 PM | P | PASS |
|
|
Life safety passed
|
BLD12-00956
| FIRE-Sprinkler Rough-in | 5/25/2012 | 5/25/2012 | 5/25/2012 3:24:54 PM | P | PASS |
|
|
Sprinkler piping is ok to cover in the restroom. I noted two areas where sprinkler coverage needs to be added/modified prior to a final sign off.
|
BLD12-00981
| FIRE-Sprinkler Rough-in | 5/25/2012 | 5/25/2012 | 5/25/2012 3:23:59 PM | P | PASS |
|
|
Sprinkler piping is ok to cover in the restroom.
|
BLD12-01294
| FIRE-Final Inspection | 5/24/2012 | 5/25/2012 | 5/25/2012 1:03:28 PM | A | FAIL |
|
|
Provide city approved plans for site inspection, provide sprinkler protection, mount the fire extinguisher, provide approved hardware. Additional items may be required when the city approved plans have been reviewed on site.
|
FIR12-00258
| INSP-Sprinkler Rough-in | 5/24/2012 | 5/25/2012 | 5/25/2012 12:49:58 PM | A | PASS |
|
|
Sprinkler piping is ok to cover at the restroom. Outside of this permits scope of work I found two locations where sprinkler coverage is lacking. Don and I discussed solutions. This will need to be addressed prior to final fire life safety sign off.
|
FIR12-00259
| INSP-Sprinkler Rough-in | 5/24/2012 | 5/25/2012 | 5/25/2012 11:54:16 AM | A | PASS |
|
|
Sprinkler piping is ok to cover.
|
BLD12-00951
| FIRE-Final Inspection | 5/24/2012 | 5/25/2012 | 5/25/2012 11:36:55 AM | A | PASS |
|
|
life safety passed
|