ESC11-00543
| General Inspection | 5/21/2012 | 5/21/2012 | | | |
|
|
|
ELE11-02047
| Final | 5/25/2012 | 5/25/2012 | 5/25/2012 3:23:16 PM | P | PASS |
|
|
lighting retro complete, final ok
|
ELE12-01217
| Final | 5/25/2012 | 5/25/2012 | 5/25/2012 3:14:11 PM | P | PASS |
|
|
We have completed the inspection of the Service to have Idaho Power turn power back on. Our Wireman that performed the work was Vince at ###-####. Thank you Phone #: ###-#### >> Inspection requested via web by Clint Tate final ok
|
ELE12-01217
| Permanent Service | 5/25/2012 | 5/25/2012 | 5/25/2012 3:13:45 PM | P | PASS |
|
|
p/s o/h rec ok
|
ELE12-01226
| Electrical Rough-In | 5/24/2012 | 5/25/2012 | 5/25/2012 2:40:54 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by John VanZandt suite 200 rough-in ok cover
|
ELE11-02081
| Final | 5/25/2012 | 5/25/2012 | 5/25/2012 1:51:55 PM | P | PASS |
|
|
Warren Phone #: ###-#### final ok power for furture
|
ELE12-01219
| Final | 5/25/2012 | 5/25/2012 | 5/25/2012 1:48:09 PM | P | PASS |
|
|
A/C units final ok
|
ELE12-01219
| Electrical Rough-In | 5/25/2012 | 5/25/2012 | 5/25/2012 1:46:15 PM | P | PASS |
|
|
Please perform the Rough-In and a Final for the HVAC Wiring. Our Wireman on-site is Rod at ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Clint Tate rough-in ok 2 A/C units above grid
|
ESC11-00750
| Aging Inspection | 5/25/2012 | 5/25/2012 | 5/25/2012 1:17:47 PM | | PASS |
|
|
site clean, landscaping in
|
ELE12-01106
| Rough-In Permanent Service | 5/24/2012 | 5/25/2012 | 5/25/2012 1:06:06 PM | A | PASS |
|
|
Roger Phone #: ###-#### p/s o/h rec ok
|
GCE12-00040
| GCE-Final | 5/25/2012 | 5/25/2012 | 5/25/2012 12:35:53 PM | P | PASS |
|
|
(Mandatory Inspection) Danny @ ###-#### Afternoon inspection for today please. Equipment tagged by third party testing, final ok
|
GCE12-00030
| GCE-Permanent Service | 5/24/2012 | 5/25/2012 | 5/25/2012 12:13:50 PM | A | PASS |
|
|
Zane @ ###-#### p/s u/g rec ok
|
ELE11-02384
| Electrical Rough-In | 5/25/2012 | 5/25/2012 | 5/25/2012 11:46:11 AM | P | PASS |
|
|
ceiling inspection. service inspections for MRI connection..roof top inspection Phone #: ###-#### >> Inspection requested via web by Shawna Gates rough-in ok cover ceiling Ultrasound room,wating room
|
ESC12-00084
| Aging Inspection | 5/25/2012 | 5/25/2012 | 5/25/2012 10:25:37 AM | | PASS |
|
|
|
ELE11-00877
| Final | 5/24/2012 | 5/25/2012 | 5/25/2012 10:13:43 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Patrick Paz final ok
|
ELE11-02687
| Final | 5/24/2012 | 5/25/2012 | 5/25/2012 10:00:29 AM | A | FAIL |
|
|
ROBERT Phone #: ###-#### Panel in detached garage requires main breaker with tie down. Circuit identification
|
ELE12-01124
| Final | 5/24/2012 | 5/25/2012 | 5/25/2012 9:39:15 AM | A | NR |
|
|
Contact is Carl Petteck ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell Not ready, no card on site
|
ELE11-02806
| Electrical Rough-In | 5/24/2012 | 5/25/2012 | 5/25/2012 9:19:58 AM | A | PASS |
|
|
Please call Mike 30 min prior so he can meet you. Mikes cell no. is ###-####. >> Inspection requested via web by Shawna Gates rough-in ok cover under counter walls 2nd floor reception area
|
ELE12-01227
| Electrical Rough-In | 5/24/2012 | 5/25/2012 | 5/25/2012 8:33:53 AM | A | PASS |
|
|
Floor heat main bath basement bath Phone #: ###-#### >> Inspection requested via web by Therrin Robertson rough-in ok cover floor heat main bath,basement bath
|
ELE12-00879
| Electrical Rough-In | 5/24/2012 | 5/25/2012 | 5/24/2012 1:49:42 PM | A | PASS |
|
|
Cell ###-#### Phone #: ###-#### >> Inspection requested via web by Mark M rough-in ok cover walls 1st floor admin offices
|