MEC18-02334
| Rough-in | 5/24/2018 | 5/25/2018 | 5/25/2018 12:16:03 PM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth Underground duct is required to slope 1/8" per foot to access port. IMC 2012 section 603.8.1
|
MIS18-00196
| MEC-Final | 5/25/2018 | 5/25/2018 | 5/25/2018 10:17:42 AM | P | PASS |
|
|
Talked to building contractor and answered questions about whether he can use the existing 3 ton furnace and a/c for the existing home and addition. Did not need to go onsite. Able to resolve all questions over the phone. Informed contractor that in my opinion the existing system is okay, but that he should still have a heating and cooling load calcs done.
|
MIS18-00196
| MEC-Conference | 5/24/2018 | 5/25/2018 | 5/25/2018 10:17:23 AM | A | DONE |
|
|
Chris Phone #: ###-#### Talked to building contractor and answered questions about whether he can use the existing 3 ton furnace and a/c for the existing home and addition. Did not need to go onsite. Able to resolve all questions over the phone. Informed contractor that in my opinion the existing system is okay, but that he should still have a heating and cooling load calcs done.
|