PLM05-01293
| Plumbing Rough-in | 5/26/2005 | 5/26/2005 | 5/27/2005 8:43:47 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/26/2005 at 10:21:07 AM. Contact: (208) ri ok
|
PLM05-01021
| Groundwork | 5/26/2005 | 5/26/2005 | 5/27/2005 7:53:46 AM | P | PASS |
|
|
below floor ok
|
PLM05-01685
| Water and/or Sewer | 5/26/2005 | 5/26/2005 | 5/26/2005 1:39:35 PM | P | PASS |
|
|
WILL BE READY FOR INSPECTION @ 1:30 PM - THANK YOU; Phone #: ###-#### Internet Inspection Request from: Holly Ryska sw final ok
|
PLM05-01686
| Water and/or Sewer | 5/26/2005 | 5/26/2005 | 5/26/2005 1:38:33 PM | P | PASS |
|
|
WILL BE READY FOR INSPECTION @ 1:30 PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska sw final ok
|
PLM05-01651
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 1:37:40 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Alderson ri ok
|
PLM05-01707
| Plumbing Rough-in | 5/26/2005 | 5/26/2005 | 5/26/2005 1:37:18 PM | P | PASS |
|
|
craig; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ri ok
|
PLM05-01736
| Water and/or Sewer | 5/26/2005 | 5/26/2005 | 5/26/2005 1:28:51 PM | P | PASS |
|
|
paige ###-#### sw final ok
|
PLM05-00924
| Final | 5/26/2005 | 5/26/2005 | 5/26/2005 11:04:29 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/26/2005 at 7:37:30 AM. Contact: ###-####. final ok
|
PLM05-00907
| Final | 5/26/2005 | 5/26/2005 | 5/26/2005 10:58:33 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/26/2005 at 7:35:34 AM. Contact: ###-####. final ok
|
PLM05-01729
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 10:48:40 AM | P | PASS |
|
|
###-#### - wyatt ri ok
|
PLM05-01458
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 10:25:15 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 8:48:59 AM. Contact: ###-####. ri sewer ok
|
PLM05-00748
| Final | 5/25/2005 | 5/26/2005 | 5/26/2005 10:16:28 AM | A | PASS |
|
|
please call for access code////jody; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles final ok
|
PLM05-01721
| Water and/or Sewer | 5/26/2005 | 5/26/2005 | 5/26/2005 9:44:28 AM | A | CANC |
|
|
WILL BE READY FOR INSPECTION @ 11:30 AM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska
|
PLM05-01653
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 9:37:01 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 4:44:16 PM. Contact: ###-####. ri ok
|
PLM05-01654
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 9:36:09 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 4:43:02 PM. Contact: ###-####.pex too close to recessed light fixture
|
PLM05-01657
| Plumbing Rough-in | 5/25/2005 | 5/26/2005 | 5/26/2005 9:07:48 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 4:41:06 PM. Contact: ###-####. ri ok
|
PLM04-03854
| Final | 5/25/2005 | 5/26/2005 | 5/26/2005 8:40:17 AM | A | PASS |
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa this is a final for most of the work on the tank. everything except the last of the intake and discharge piping. micron is taking over the job.
|
PLM05-01736
| DOC - Permit Finaled | 5/26/2005 | 5/26/2005 | 5/26/2005 12:00:00 AM | P | PASS |
|
|
paige ###-####
|
PLM05-01686
| DOC - Permit Finaled | 5/26/2005 | 5/26/2005 | 5/26/2005 12:00:00 AM | P | PASS |
|
|
WILL BE READY FOR INSPECTION @ 1:30 PM - THANK YOU!; Phone #: ###-#### Internet Inspection Request from: Holly Ryska
|