Inspections for the day of: Thursday, May 26, 2005.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-00497 FIRE-Final Inspection5/25/20055/26/20055/26/2005 4:19:44 PMPFAIL
Final pending repair of one exit sign above the main entry/exit.
FIR05-00258 INSP-Sprinkler Rough-in/Hydro5/26/20055/26/20055/26/2005 4:07:41 PMPPART
Overhead hydrostatic test passed inspection. Still need to perform 24 hr. air test.
BLD04-00029 FIRE-Final Inspection5/26/20055/26/20055/26/2005 4:02:02 PMPPASS
20th floor passed inspection. Fire life safety finaled.
BLD05-00803 FIRE-Final Inspection5/25/20055/26/20055/26/2005 1:13:47 PMPFAIL
Need to install fire extinguisher, verify approved door hardware at storage room and break room, provide approved type remote annunciators for duct smoke detectors.
BLD04-00029 FIRE-Final Inspection5/25/20055/26/20055/26/2005 10:19:50 AMAPART
19th floor passed inspection, 20th floor needs max occupant load sign posted in board room.
FIR05-00292 INSP-Final Inspection5/25/20055/26/20055/26/2005 9:08:54 AMAPASS
Fire sprinkler passed inspection. Tom D. with Idaho Fire Protection to supply spare SW 20 head in headbox .
FIR05-00258 INSP-Sprinkler Rough-in5/26/20055/26/20055/26/2005 12:00:00 AMPFAIL
Provide forward flow apparatus as required by review note #74, provide EQ brace on 4" main north side last piece, provide plans showing two SW heads at overhead door.
FIR05-00225 INSP-Final Inspection5/26/20055/26/20055/26/2005 12:00:00 AMPPASS
Fire sprinkler finaled.