FIR11-00137
| INSP-Final Inspection | 5/26/2011 | 5/26/2011 | 5/26/2011 5:13:49 PM | P | PART |
|
|
Final pending installation matching approved plans. Drawings indicate 1 1/2" piping to supply the new pendent heads. Field install was completed using 1". Provide revised plans or modify work to reflect the design.
|
FIR08-00239
| INSP-Sprinkler Rough-in | 5/26/2011 | 5/26/2011 | 5/26/2011 4:53:46 PM | P | PART |
|
|
OH piping at building #3 east stairway floors basement thru 3rd floor okayed for cover.
|
BLD11-00581
| FIRE-Final Inspection | 5/26/2011 | 5/26/2011 | 5/26/2011 4:51:46 PM | P | PASS |
|
|
Life safety inspection passed. Fire extinguisher posted as discussed.
|
FIR11-00146
| INSP-Final Inspection | 5/25/2011 | 5/26/2011 | 5/26/2011 4:50:34 PM | P | PASS |
|
|
Fire alarm work passed field testing. Permit finaled.
|
FIR10-00137
| INSP-Alarm Testing | 5/25/2011 | 5/26/2011 | 5/26/2011 4:48:51 PM | A | PART |
|
|
Completed testing of ID and DD devices at the basement levels. Noted tamper valve at the elevator machine room to be monitored, as-builts to reflect deleted and added devices, dampers have been repaired and verified for functionality. Previously noted correction items underway, some are finished. Ref. plan set for annotations.
|
FIR11-00170
| INSP-Sprinkler Rough-in | 5/25/2011 | 5/26/2011 | 5/26/2011 4:43:01 PM | A | CANC |
|
|
See stamped plans for overhead work at grid ceilings okayed for cover marked with today's date.
|