FIR09-00189
| INSP-Supply line flush | 5/21/2009 | 5/27/2009 | 5/27/2009 4:18:39 PM | P | FAIL |
|
|
No water available for the underground flush, preliminary walkthrough for the overhead installation done, riser is not finished at this time.
|
FIR08-00605
| INSP-Sprinkler Rough-in/Hydro | 5/26/2009 | 5/27/2009 | 5/27/2009 4:16:25 PM | A | PART |
|
|
Inspection for the remainder of tenting work completed satisfactory, overhead work approved for cover, see notice left on site.
|
BLD08-00942
| FIRE-Alarm Testing | 5/26/2009 | 5/27/2009 | 5/27/2009 4:14:26 PM | A | PASS |
|
|
Fire alarm interconnection at the magnetic door hold opertated correctly.
|
BLD08-00942
| FIRE-Final Inspection | 5/26/2009 | 5/27/2009 | 5/27/2009 4:13:22 PM | A | PASS |
|
|
Fire life safety inspection completed acceptable for the vanilla permit.
|
BLD09-00265
| FIRE-Final Inspection | 5/26/2009 | 5/27/2009 | 5/27/2009 4:12:10 PM | A | FAIL |
|
|
Missing the fire extinguisher, one EM light at the front reception area needs repair.
|
FIR08-00786
| INSP-Alarm Testing | 5/26/2009 | 5/27/2009 | 5/27/2009 4:10:22 PM | A | PART |
|
|
Completed fire alarm testing for areas D and E first floor including the elevator-see plans for annotations. Noted one fire damper at the electrical room adjacent to the riser room which did not operate, retest for items noted yesterday okayed, as-builts for deleted points to be reflected on record drawings.
|