PLM11-00572
| Final | 5/26/2011 | 5/27/2011 | 5/27/2011 4:31:09 PM | A | PART |
|
|
late morning--peter Phone #: ###-#### additional backflow need double check on water supply to ice machine need R P to water cooled condensing unit,s need double check on refrimalizor . need 120 degree hot water limitation to hand sink,s contractor to recall when ready
|
PLM11-00103
| Final | 5/27/2011 | 5/27/2011 | 5/27/2011 3:08:12 PM | P | PASS |
|
|
Steve Phone #: ###-####
|
PLM11-00792
| Water and/or Sewer | 5/27/2011 | 5/27/2011 | 5/27/2011 2:41:37 PM | P | PART |
|
|
John Phone #: ###-#### grease interceptor ,two inch water main to new building, and storm drain,s on north-west side of building test ok ok to cover
|
PLM11-00926
| Water and/or Sewer | 5/26/2011 | 5/27/2011 | 5/27/2011 2:00:50 PM | P | PASS |
|
|
Lock box to right of front door on wall code-1944. Will''s Cell# ###-#### Phone #: ###-#### >> Inspection requested via web by AnnMarie McCaw
|
PLM11-00926
| Water Heater Final | 5/27/2011 | 5/27/2011 | 5/27/2011 2:00:35 PM | P | PASS |
|
|
|
PLM11-00922
| Sprinkler (Final) | 5/26/2011 | 5/27/2011 | 5/27/2011 1:35:50 PM | P | PASS |
|
|
|
PLM11-00938
| Groundwork | 5/27/2011 | 5/27/2011 | 5/27/2011 1:10:54 PM | P | PASS |
|
|
Ken Phone #: ###-####
|
PLM11-00936
| Plumbing Rough-in | 5/26/2011 | 5/27/2011 | 5/27/2011 12:23:40 PM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Jeff Coate
|
PLM11-00859
| Final | 5/27/2011 | 5/27/2011 | 5/27/2011 11:45:41 AM | A | PASS |
|
|
Thanks, Jim ###-#### >> Inspection requested via web by James Romano
|
PLM11-00271
| Final | 5/27/2011 | 5/27/2011 | 5/27/2011 11:37:50 AM | A | PASS |
|
|
Thanks, Jim ###-#### >> Inspection requested via web by James Romano
|
PLM11-00533
| Final | 5/26/2011 | 5/27/2011 | 5/27/2011 11:06:20 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by JIM LITTLE
|
PLM11-00849
| Plumbing Rough-in | 5/26/2011 | 5/27/2011 | 5/27/2011 10:50:14 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Kristy Watson
|
PLM10-02603
| Final | 5/26/2011 | 5/27/2011 | 5/27/2011 10:38:47 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by James Paulin
|
GCP11-00054
| GCP-Under Floor | 5/25/2011 | 5/27/2011 | 5/27/2011 10:01:40 AM | A | CANC |
|
|
GroundworkContractor ###-####Call in advance canc by contractor
|
PLM09-01956
| Plumbing Rough-in | 5/27/2011 | 5/27/2011 | 5/27/2011 10:00:48 AM | P | PASS |
|
|
Early afternoon---Jim Phone #: ###-####
|
PLM11-00712
| Final | 5/27/2011 | 5/27/2011 | 5/27/2011 9:31:40 AM | P | PASS |
|
|
brian Phone #: ###-####
|
PLM11-00904
| Plumbing Rough-in | 5/26/2011 | 5/27/2011 | 5/27/2011 9:24:49 AM | A | PASS |
|
|
JOB # 15916. Phone #: ###-#### >> Inspection requested via web by Ann Marie Reyes
|
PLM11-00599
| Plumbing Rough-in | 5/26/2011 | 5/27/2011 | 5/27/2011 8:55:50 AM | A | PASS |
|
|
restroom,s test ok ok to cover
|
PLM11-00902
| Final | 5/23/2011 | 5/27/2011 | 5/27/2011 8:34:03 AM | A | PASS |
|
|
Nile Phone #: ###-####
|
PLM11-00935
| Final | 5/26/2011 | 5/27/2011 | 5/27/2011 8:16:00 AM | A | PASS |
|
|
john Phone #: ###-####
|