PLM03-00705
| PLM-Aging Inspection | 5/28/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | | PASS |
|
|
work still in progress 5/28/2003 9:20:06 AM
|
PLM03-00706
| PLM-Aging Inspection | 5/28/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | | PASS |
|
|
work still in progress 5/28/2003 9:20:28 AM
|
PLM03-01187
| Plumbing Rough-in | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 5/27/2003 at 11:47:23 AM. Contact: ###-####. rough-in retest on room,s 510&511 test ok start of med gas pressure test on rooom,s 507 tthrough 511 5/28/2003 12:21:16 PM
|
PLM03-01516
| Sprinkler (Final) | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM03-01521
| Water and/or Sewer | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | PASS |
|
|
###-#### dan
|
PLM03-01522
| Water and/or Sewer | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | PASS |
|
|
###-#### dan
|
PLM03-01523
| Sprinkler (Final) | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | PASS |
|
|
###-#### justin
|
PLM03-01524
| Plumbing Rough-in | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | NR |
|
|
###-#### ken not ready 5/28/2003 9:39:54 AM
|
PLM03-01525
| Plumbing Rough-in | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | A | NR |
|
|
###-#### ken not ready 5/28/2003 9:39:42 AM
|
PLM03-01527
| Water and/or Sewer | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | P | CANC |
|
|
###-#### bj
|
PLM03-01533
| Water and/or Sewer | 5/28/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | P | PASS |
|
|
###-#### jim
|
PLM03-01518
| Plumbing Rough-in | 5/28/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/28/2003 at 8:36:19 AM. Contact: ###-####.
|
PLM03-00312
| Roof Drains | 5/27/2003 | 5/28/2003 | 5/28/2003 12:00:00 AM | P | FAIL |
|
|
need to remove tee,s in storm drain system and re place with directional approved fitting,s 5/28/2003 5:19:51 PM
|