Inspections for the day of: Friday, May 28, 2010.
Number of inspections: 30
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-01273 BLD-Aging Inspection5/28/20105/28/20106/3/2010 6:35:57 PM PASS
R105.5 Expiration.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

R105.8 Responsibility.
It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.
BLD06-01382 BLD-Aging Inspection5/28/20105/28/20106/3/2010 6:35:05 PM PASS
R105.5 Expiration.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

R105.8 Responsibility.
It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.
BLD06-01396 BLD-Aging Inspection5/28/20105/28/20106/3/2010 9:59:28 AM PASS
terry sign off pw
BLD10-01113 BLD-Final5/28/20105/28/20105/28/2010 4:10:18 PMPPASS
BLD10-01113 DOC - Permit Finaled5/28/20105/28/20105/28/2010 4:10:08 PMPPASS
BLD09-01803 BLD-Final5/28/20105/28/20105/28/2010 3:55:02 PMPPASS
BLD09-01803 DOC - Permit Finaled5/28/20105/28/20105/28/2010 3:54:50 PMPPASS
ESC10-00246 Random Inspection5/27/20105/28/20105/28/2010 3:53:56 PMAFAIL
non compliance w/cn and rp's verball agreement to comply. stopwork and hold on job permits until removed.
BLD10-00723 BLD-Footing5/28/20105/28/20105/28/2010 3:39:48 PMPPASS
ESC10-00276 Site Preparation5/28/20105/28/20105/28/2010 3:39:32 PMPPASS
ESC10-00323 Random Inspection5/28/20105/28/20105/28/2010 2:56:10 PMPPASS
BLD10-00844 BLD-Framing/Rough-in5/28/20105/28/20105/28/2010 2:55:51 PMPFAIL
kelly Phone #: ###-#### headers and trimmer/king studs not per plan.// trusses not supported// mlg not supported at ladder framing. cahalk and seal.
ESC09-00780 Random Inspection5/28/20105/28/20105/28/2010 2:05:26 PMPPASS
BLD09-02179 BLD-Framing/Rough-in5/28/20105/28/20105/28/2010 2:05:12 PMPPASS
Call Dave 30min. prior to going out. Phone #: ###-####
BLD09-02179 BLD-Energy code compliance5/28/20105/28/20105/28/2010 2:04:59 PMPPASS
Call Dave 30min. prior to going out. Phone #: ###-####
BLD10-01113 BLD-Final5/27/20105/28/20105/28/2010 11:26:28 AMADEFR
Inspection requested from web by: cassandra burak Phone #: ###-####
BLD10-00723 BLD-Footing5/27/20105/28/20105/28/2010 11:26:11 AMADEFR
chad - as late as possible please Phone #: ###-####
BLD09-01803 BLD-Final5/27/20105/28/20105/28/2010 11:25:43 AMADEFR
Nate Phone #: ###-####
BLD10-00797 BLD-Final5/26/20105/28/20105/28/2010 11:24:47 AMACANC
Jim; this is a final for a small TI Restaurant space, tres bonne cuisine. If the timing works, we can cover this along with the Supervalu office inspection finals.
Thanks
Craig Brown Inspection requested from web by: Craig Brown Phone #: ###-####
BLD09-02291 BLD-Final5/26/20105/28/20105/28/2010 11:20:21 AMAPASS
Jim; Forest recently completed the life safety final for this Buidling- Riverview. I''d like to combine with another final at the main Supervalu Bldg. Please let me know atime Friday that works in your schedule so I can be ther.
Thanks Craig Inspection requested from web by: Craig Brown Phone #: ###-####
BLD09-02291 DOC - Permit Finaled5/28/20105/28/20105/28/2010 11:20:05 AMPPASS
BLD10-00406 BLD-Final5/26/20105/28/20105/28/2010 11:19:35 AMAPASS
Jim; this is a final for one of the Supervalu Office remodel phases. I would like to combine this with another inspection I just requested for the Riverview Building. Please let me know a time that works in your schedule so I can meet you there.
Thanks
Craig Brown Inspection requested from web by: Craig Brown Phone #: ###-####
BLD10-00406 DOC - Permit Finaled5/28/20105/28/20105/28/2010 11:19:25 AMPPASS
BLD10-01098 BLD-Final5/27/20105/28/20105/28/2010 11:13:38 AMAPASS
Doug Phone #: ###-####
BLD10-01098 DOC - Permit Finaled5/28/20105/28/20105/28/2010 11:13:10 AMPPASS
BLD09-01611 BLD-Final5/27/20105/28/20105/28/2010 9:06:05 AMAPASS
Inspection requested from web by: Mike Shain Phone #: ###-####
BLD09-01611 DOC - Permit Finaled5/28/20105/28/20105/28/2010 9:05:56 AMPPASS
BLD06-00888 DOC - Permit Expired5/27/20105/28/20105/28/2010 8:24:05 AMAPASS
R105.5 Expiration.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

R105.8 Responsibility.
It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.
BLD06-01255 DOC - Permit Expired5/27/20105/28/20105/28/2010 8:23:26 AMAPASS
R105.5 Expiration.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

R105.8 Responsibility.
It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.
BLD06-01091 DOC - Permit Expired5/27/20105/28/20105/28/2010 8:22:48 AMAPASS
R105.5 Expiration.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

R105.8 Responsibility.
It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical or plumbing systems, for which this code is applicable, to comply with this code.