FIR14-00284
| INSP-Sprinkler Rough-in | 5/28/2014 | 5/28/2014 | 5/28/2014 3:13:34 PM | P | PASS |
|
|
Underground piping is ok to cover
|
FIR14-00140
| INSP-Final Inspection | 5/27/2014 | 5/28/2014 | 5/28/2014 3:06:36 PM | P | FAIL |
|
|
Permit not ready to final due to ceiling tile not being installed yet.
|
FIR14-00131
| INSP-Final Inspection | 5/28/2014 | 5/28/2014 | 5/28/2014 2:24:50 PM | P | FAIL |
|
|
Canceled by Brian as I pulled up. Per Brian two more pull stations are going to be added. I noted that the new pull stations currently installed too high. Also the smoke detector shown as existing located over the FACP is not installed and will unless documentation is provided showing is does not need to be installed. No actual testing was performed.
|
FIR14-00076
| INSP-Sprinkler Rough-in | 5/28/2014 | 5/28/2014 | 5/28/2014 2:14:49 PM | P | PASS |
|
|
Overhead rough-in passed for the 4" wet system from the riser room to the new "infill".
|
FIR13-00723
| INSP-Sprinkler Rough-in | 5/27/2014 | 5/28/2014 | 5/28/2014 12:10:09 PM | A | PASS |
|
|
See the city approved plans for additional locations where piping can be covered.
|
BLD14-00321
| FIRE-Final Inspection | 5/27/2014 | 5/28/2014 | 5/28/2014 9:53:07 AM | A | PASS |
|
|
Life safety passed. Panic only hardware is to be installed on door from Lobby to back offices per Carl Westfall.
|
BLD13-03265
| FIRE-Final Inspection | 5/27/2014 | 5/28/2014 | 5/28/2014 9:52:01 AM | A | FAIL |
|
|
Provide building address 4" minimum and contrasting color facing street. Remove the thumbturn lock on the main exit, keyed is ok with an indicator and sticker. Access controled egress doors to meet IFC 1008.1.9.8 (need sensor and request to exit buttons). Provide testing of the new duct smoke detectors.
|