Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00266 INSP-Final Inspection5/29/20095/29/20095/29/2009 3:38:47 PMPPASS
Permit finaled.
FIR08-00469 INSP-Final Inspection5/27/20095/29/20095/29/2009 2:57:58 PMPPASS
Permit finaled.
BLD08-01210 FIRE-Final Inspection5/28/20095/29/20095/29/2009 2:57:36 PMAPASS
Life safety passed.
BLD08-02057 FIRE-Conference5/28/20095/29/20095/29/2009 2:15:22 PMADONE
I deferred Tom to Mark Senteno for the temp until the fire lane is complete.
BLD09-00123 FIRE-Final Inspection5/29/20095/29/20095/29/2009 2:13:13 PMPPASS
Life safety passed.
FIR09-00091 INSP-Alarm Testing5/26/20095/29/20095/29/2009 2:10:32 PMAPASS
Permit finaled
FIR09-00093 INSP-Alarm Testing5/26/20095/29/20095/29/2009 11:20:20 AMAPASS
Permit finaled.
BLD08-02577 FIRE-Final Inspection5/28/20095/29/20095/29/2009 11:19:53 AMAFAIL
Provide tag for the fire extinguisher, provide exit discharge light at the west most exit and provide address as discussed.
FIR09-00179 INSP-Final Inspection5/28/20095/29/20095/29/2009 10:41:50 AMAPASS
Permit finaled
FIR09-00266 INSP-Alarm Testing5/29/20095/29/20095/29/2009 10:41:27 AMAPASS
Permit finaled
BLD09-00393 FIRE-Final Inspection5/28/20095/29/20095/29/2009 10:38:28 AMAPART
A temporary occupancy was given until the sprinkler protection in the two new rooms is modified.
FIR09-00109 FIR-Aging Inspection5/29/20095/29/20095/29/2009 8:03:31 AM NR
work is in progress
BLD09-00123 FIRE-Final Inspection5/28/20095/29/20095/29/2009 7:29:47 AMAFAIL
No one at the site knew where the plans were at. I left a message on Scott's voice mail.