Inspections for the day of: Tuesday, May 29, 2012.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR12-00227 INSP-Sprinkler Rough-in/Hydro5/29/20125/29/20125/29/2012 3:45:35 PMPPASS
Overhead hydro test passed.
FIR12-00059 INSP-Sprinkler Rough-in/Hydro5/29/20125/29/20125/29/2012 3:26:42 PMPPASS
First floor dry system hydro test passed on the second try. Ken found and fixed the leak.
FIR11-00496 INSP-Sprinkler Rough-in/Hydro5/29/20125/29/20125/29/2012 3:18:23 PMPPASS
Overhead hydro test passed on the second try.
FIR12-00059 INSP-Sprinkler Rough-in/Hydro5/29/20125/29/20125/29/2012 1:07:44 PMAFAIL
Dry system hydro test failed due to visable drop of pressure on the guage. Rescheduled for this afternoon.
FIR11-00496 INSP-Sprinkler Rough-in/Hydro5/29/20125/29/20125/29/2012 1:07:09 PMAFAIL
Dry system hydro test failed due to visable drop of pressure on the guage. Rescheduled for this afternoon.
FIR11-00568 FIR-Aging Inspection5/29/20125/29/20125/29/2012 10:27:46 AM NR
I spoke to Jason at Peak Alarm and he was going to get with Mike and follow up on the project status.
FIR11-00078 FIR-Aging Inspection5/29/20125/29/20125/29/2012 10:24:25 AM NR
Left message on Jeff's voice mail requesting project status.
BLD12-01209 FIRE-Final Inspection5/25/20125/29/20125/29/2012 10:20:04 AMAPASS
life safety passed