FIR13-00216
| INSP-Sprinkler Rough-in | 5/29/2013 | 5/29/2013 | 5/30/2013 12:30:10 PM | P | PART |
|
|
Overhead fire sprinkler work above the grid ceilings okayed for cover.
|
FIR13-00101
| INSP-Sprinkler Rough-in | 5/29/2013 | 5/29/2013 | 5/29/2013 4:58:30 PM | P | PART |
|
|
Point of connection to building riser stub okayed for bury- flushing to be completed prior to final.
|
BLD13-00807
| FIRE-Conference | 5/29/2013 | 5/29/2013 | 5/29/2013 12:37:04 PM | P | DONE |
|
|
Discussion with contractor regarding fire extinguisher placement, project related trade work and finish schedule.
|
BLD13-01264
| FIRE-Final Inspection | 5/29/2013 | 5/29/2013 | 5/29/2013 12:24:41 PM | A | PART |
|
|
Final pending remainder of noted correction items including hardware and main entry/exit signage.
|
FIR13-00116
| INSP-Sprinkler Rough-in | 5/29/2013 | 5/29/2013 | 5/29/2013 12:19:05 PM | A | PART |
|
|
UG including the tie-in and 45 ell okay for cover. Overhead work in progress.
|
BLD13-00868
| FIRE-Final Inspection | 5/29/2013 | 5/29/2013 | 5/29/2013 12:14:50 PM | A | PASS |
|
|
Phase one and two completed, inspection passed.
|
BLD11-00407
| FIRE-Final Inspection | 5/29/2013 | 5/29/2013 | 5/29/2013 12:13:17 PM | A | PASS |
|
|
Life safety inspection completed and passed.
|