BLD06-00450
| BLD-Aging Inspection | 5/29/2013 | 5/29/2013 | 6/6/2013 7:35:43 AM | | PEND |
|
|
|
BLD13-00805
| BLD-Framing/Rough-in | 5/28/2013 | 5/29/2013 | 5/30/2013 7:04:04 AM | P | PART |
|
|
Doug Phone #: ###-#### ok to cover walls after other trades ok thier rough ins
|
BLD13-00018
| BLD-Framing/Rough-in | 5/28/2013 | 5/29/2013 | 5/30/2013 7:03:05 AM | P | NR |
|
|
mike Phone #: ###-#### needs a mec rough in no inspection done
|
GCB13-00067
| GCB-Fndatn/slab ins/fld vent | 5/29/2013 | 5/29/2013 | 5/29/2013 3:03:03 PM | P | PASS |
|
|
|
GCB13-00067
| GCB-Framing | 5/29/2013 | 5/29/2013 | 5/29/2013 3:02:19 PM | A | CANC |
|
|
John ###-####-Foundation wall inspection
|
BLD13-01060
| BLD-Final | 5/29/2013 | 5/29/2013 | 5/29/2013 2:58:35 PM | P | PASS |
|
|
|
BLD13-01060
| DOC - Permit Finaled | 5/29/2013 | 5/29/2013 | 5/29/2013 2:58:17 PM | P | PASS |
|
|
|
BLD13-01060
| BLD-Conference | 5/28/2013 | 5/29/2013 | 5/29/2013 2:57:46 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher
|
BLD13-00804
| BLD-Final | 5/28/2013 | 5/29/2013 | 5/29/2013 2:13:56 PM | P | PASS |
|
|
Doug Phone #: ###-####
|
GCB13-00011
| GCB-Final | 5/29/2013 | 5/29/2013 | 5/29/2013 1:32:29 PM | P | PASS |
|
|
Devin Phone #: ###-####
|
BLD13-00883
| BLD-Framing/Rough-in | 5/28/2013 | 5/29/2013 | 5/29/2013 1:20:43 PM | A | PART |
|
|
Daryl Phone #: ###-#### ok all but needs to fix fireproofing on column
|
GCB13-00015
| GCB-Final | 5/29/2013 | 5/29/2013 | 5/29/2013 1:16:00 PM | P | PASS |
|
|
Phone #: ###-####
|
BLD13-01014
| BLD-Foundation | 5/28/2013 | 5/29/2013 | 5/29/2013 9:40:46 AM | A | PASS |
|
|
chris Phone #: ###-####
|
BLD13-00704
| BLD-Wall Bracing | 5/28/2013 | 5/29/2013 | 5/29/2013 9:40:07 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
BLD13-00516
| BLD-Energy code compliance | 5/29/2013 | 5/29/2013 | 5/29/2013 9:09:43 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|