BLD17-04226
| BLD-Other | 5/29/2019 | 5/29/2019 | 5/29/2019 3:32:50 PM | P | PASS |
|
|
Vicky-block and tie Phone #: ###-####
|
BLD16-03452
| BLD-Other | 5/29/2019 | 5/29/2019 | 5/29/2019 3:32:37 PM | P | PASS |
|
|
Vicky-block and tie Phone #: ###-####
|
BLD19-00685
| FIRE-Final Inspection | 5/29/2019 | 5/29/2019 | 5/29/2019 3:01:59 PM | P | PASS |
|
|
Lloyd Phone #: ###-####. All issues resolved.
|
BLD18-02696
| BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 2:17:43 PM | P | PASS |
|
|
Chad- please call for access Phone #: ###-####
|
BLD18-02696
| DOC - Permit Finaled | 5/29/2019 | 5/29/2019 | 5/29/2019 2:17:35 PM | P | PASS |
|
|
|
BLD18-02696
| FIRE-Final Inspection | 5/29/2019 | 5/29/2019 | 5/29/2019 2:17:25 PM | P | PASS |
|
|
Chad- please call for access Phone #: ###-####. The fire extinguisher with current inspection tag has been placed as previously noted.
|
BLD18-04391
| BLD-Final | 5/29/2019 | 5/29/2019 | 5/29/2019 2:01:51 PM | P | PASS |
|
|
Kai Phone #: ###-####
|
BLD18-04391
| BLD-Blower Door Test Results | 5/29/2019 | 5/29/2019 | 5/29/2019 2:01:42 PM | P | DONE |
|
|
3.17
|
BLD18-04391
| DOC - Permit Finaled | 5/29/2019 | 5/29/2019 | 5/29/2019 2:00:02 PM | P | PASS |
|
|
|
BLD19-00595
| BLD-Framing/Rough-in | 5/29/2019 | 5/29/2019 | 5/29/2019 1:43:51 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Complete lateral bracing on A08 truss. Fireblock dryer vent chase at ceiling. Install squash blocks on D04 truss, east side. F02 truss placed in wrong location. Complete nailinf of interior shear wall in master bedroom.
|
BLD19-00124
| BLD-Framing/Rough-in | 5/28/2019 | 5/29/2019 | 5/29/2019 11:06:36 AM | A | PART |
|
|
Mark Phone #: 208-###-####. H2.5 installed. Ok to cover pending electrical rough in inspections.
|
BLD18-03545
| BLD-Wall cover | 5/29/2019 | 5/29/2019 | 5/29/2019 11:05:51 AM | A | PASS |
|
|
Roof only ok to dry sheet.
|
BLD18-02091
| BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 10:01:49 AM | A | PASS |
|
|
Tim Phone #: ###-####. OK for perm occ.
|
BLD18-02091
| FIRE-Final Inspection | 5/29/2019 | 5/29/2019 | 5/29/2019 10:01:34 AM | A | PASS |
|
|
Tim Phone #: ###-####. All issues resolved.
|
BLD18-03908
| BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 9:42:53 AM | A | PASS |
|
|
Brian Phone #: ###-####
|
BLD19-00397
| BLD-Framing/Rough-in | 5/28/2019 | 5/29/2019 | 5/29/2019 9:00:32 AM | A | PEND |
|
|
Victor Phone #: ###-####. Electrical work? If so, complete and have inspected.
|
BLD19-00397
| BLD-Wall Bracing | 5/28/2019 | 5/29/2019 | 5/29/2019 8:59:35 AM | A | FAIL |
|
|
Victor Phone #: ###-####. Provide portal frame at garage door opening. Correction notice posted.
|
BLD18-04533
| BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 8:36:29 AM | A | FAIL |
|
|
Greg-call for access Phone #: ###-####. Provide the blower door test results and post. Complete grading. Need to provide min. 2% slope from foundation. Correction notice posted.
|