BLD99-00767
| INSP - Framing/Rough-in | 5/3/1999 | 5/3/1999 | 5/5/1999 12:00:00 AM | P | FAIL |
|
|
05/03/99 301 - Tony ###-####
|
BLD99-00721
| INSP - Final | 4/30/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | A | FAIL |
|
|
05/03/99 301 - finaled by tom a.
|
BLD99-00983
| INSP - Final | 5/3/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | PASS |
|
|
05/03/99 301 - Dan ###-####
|
BLD99-00768
| INSP - Framing/Rough-in | 5/3/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | PASS |
|
|
05/03/99 301 - framing ok
|
BLD98-01993
| INSP - Framing/Rough-in | 4/30/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | PART |
|
|
05/03/99 301 - c/n fire wall
|
BLD99-00077
| INSP - Framing/Rough-in | 5/3/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | PASS |
|
|
05/03/99 301 - framing ok
|
BLD99-00151
| INSP - Concrete | 5/3/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | PASS |
|
|
05/03/99 301 - FDN -OK FOUNDATION
|
MIS99-00088
| INSP - Conference | 5/3/1999 | 5/3/1999 | 5/4/1999 12:00:00 AM | P | CANC |
|
|
|
BLD99-00562
| INSP - Final | 5/3/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | | PASS |
|
|
/ / 301 - FINAL OK
|
MEC99-00898
| INSP - Final | 4/30/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | A | FAIL |
|
|
05/03/99 301 - TRANS TO RUSS IN THE AREA.
|
MEC99-00898
| INSP - Final | 4/30/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | A | FAIL |
|
|
05/03/99 301 - TRANS TO RUSS IN THE AREA.
|
BLD99-00357
| INSP - Framing/Rough-in | 4/30/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | A | PASS |
|
|
05/03/99 301 - Scheduled by Hello!. Contact phone is [8704218].
|
BLD99-00472
| INSP - Final | 4/30/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | A | PASS |
|
|
05/03/99 301 - reroof ok final
|
BLD99-00828
| INSP - Final | 4/30/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | A | FAIL |
|
|
05/03/99 301 - called and left measage could not locate or access if it
|
MIS99-00052
| INSP - Final | 5/3/1999 | 5/3/1999 | 5/3/1999 12:00:00 AM | P | PASS |
|
|
|