BLD05-00631
| BLD-Aging Inspection | 5/3/2006 | 5/3/2006 | 5/4/2006 2:57:39 PM | | NR |
|
|
I spoke to the secretary and she had me leave a message on Gale's voice mail requesting the status of the job. I also spoke with the warehouse manager Lance about getting the permit finaled.
|
FIR05-00850
| INSP-Supply line flush | 5/3/2006 | 5/3/2006 | 5/3/2006 4:15:42 PM | P | PASS |
|
|
Underground flush passed. Underground hydro test passed.
|
FIR06-00239
| INSP-Supply line flush | 5/3/2006 | 5/3/2006 | 5/3/2006 4:15:07 PM | P | PASS |
|
|
Underground flush passed. Underground hydro test passed.
|
FIR06-00229
| INSP-Sprinkler Rough-in/Hydro | 5/3/2006 | 5/3/2006 | 5/3/2006 3:28:18 PM | P | PASS |
|
|
Above ground hydro test passed. I performed a partial rough-in inspection. The EFSR heads were too close to the truss webbing. Some EQ bracing still needed to be installed.
|
FIR06-00086
| INSP-Sprinkler Rough-in/Hydro | 5/2/2006 | 5/3/2006 | 5/3/2006 2:07:10 PM | A | PASS |
|
|
Sprinkler piping is ok to cover up to the engine bays. Underground hydro test and flush passed.
|
FIR06-00086
| INSP-Supply line flush | 5/2/2006 | 5/3/2006 | 5/3/2006 12:15:59 PM | A | PASS |
|
|
Supply line hydro test and flush passed.
|
FIR06-00229
| INSP-Sprinkler Rough-in/Hydro | 5/3/2006 | 5/3/2006 | 5/3/2006 12:00:00 AM | P | CANC |
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles wants to rescheduled for 5/4/2006
|