Inspections for the day of: Tuesday, May 3, 2016.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRex Boyles
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE16-00644 Final5/3/20165/3/20165/3/2016 4:02:10 PMPPASS
please call Steve Girard for access ###-#### if you have any questions please call Brad ###-#### Phone #: ###-#### Inspection requested via web by Brad Baker final ok
ELE11-00142 ELE-Aging Inspection5/3/20165/3/20165/3/2016 3:31:23 PM DONE
too busy
ELE13-02452 ELE-Aging Inspection5/3/20165/3/20165/3/2016 3:30:37 PM DONE
did drive by final ok
ELE13-02452 Final5/3/20165/3/20165/3/2016 3:30:09 PMPPASS
did drive by final ok
ELE16-01356 Electrical Rough-In5/3/20165/3/20165/3/2016 3:29:10 PMPPASS
2nd floor rough in Phone #: ###-#### Inspection requested via web by Brandon Winters r/i ok cut in boxes and 2 home run conduits
ELE16-01356 Final5/3/20165/3/20165/3/2016 3:27:58 PMPPASS
2nd floor rough in Phone #: ###-#### Inspection requested via web by Brandon Winters final ok
ELE15-03901 Electrical Rough-In5/3/20165/3/20165/3/2016 3:23:06 PMPPASS
Call Joey for R/I inspection of 9th floor executive stairwell. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 9th flr and penthouse stairwells Also discuss with Joey loadcenter in "closet". OK because electrical and associated equipment only
ELE16-01401 Conference5/3/20165/3/20165/3/2016 2:21:20 PMPDONE
Scott// please call before Phone #: ###-#### Explain requirements for temp./perm. power pole, ground rods, riser and underground service to new house
ELE16-00886 Electrical Rough-In5/3/20165/3/20165/3/2016 1:58:11 PMPPASS
Bud Phone #: ###-#### r/i garage ok
ELE16-00886 Permanent Service5/3/20165/3/20165/3/2016 1:57:32 PMPPASS
Bud Phone #: ###-#### p/s o/h n ok relocate drop to garage main panel
ELE16-01377 Final5/2/20165/3/20165/3/2016 10:37:34 AMAPASS
Please call Cheryl at ###-#### half an hour before arrival for access. If you have questions please call Jeremiah at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Dan Mitchell final ok
ELE16-01377 Electrical Rough-In5/2/20165/3/20165/3/2016 10:35:36 AMAPASS
Please call Cheryl at ###-#### half an hour before arrival for access. If you have questions please call Jeremiah at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Dan Mitchell r/i u.ground ok
ELE15-03858 Permanent Service5/2/20165/3/20165/3/2016 10:18:18 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton p/s u/g n ok 120/240 volt 1 phase parking lot lighting service on northwest corner of bldg. ALSO:"partial final" rooftop final ok
ELE16-01160 Final5/2/20165/3/20165/3/2016 9:24:22 AMAPASS
Contact: Derrick Kamper Phone #: ###-#### Inspection requested via web by Deb Gooden final ok
ELE16-01160 Permanent Service5/3/20165/3/20165/3/2016 9:23:09 AMPPASS
Contact: Derrick Kamper Phone #: ###-#### Inspection requested via web by Deb Gooden p/s u/g n ok existing service, add 1 phase meter to 3 phase system. available fault current for existing service exceeds AIC rating.
ELE16-00208 Final5/1/20165/3/20165/3/2016 8:52:40 AMAPASS
Phone #: ###-#### Inspection requested via web by Craig Korell final ok
ELE16-01231 Final5/2/20165/3/20165/3/2016 8:29:24 AMAPASS
Please contact Vern Ricketts for access ###-#### Phone #: ###-#### Inspection requested via web by steve ragan corrections made final ok
ELE16-01381 Final5/2/20165/3/20165/3/2016 8:28:08 AMAPASS
Please contact Vern Ricketts for access ###-#### Phone #: ###-#### Inspection requested via web by steve ragan final ok for garage recepts.
ELE16-01383 Final5/2/20165/3/20165/3/2016 7:51:39 AMACANC
Inspection requested via web by Dustin Kuester needed t/s
ELE16-01383 Temporary Service5/3/20165/3/20165/3/2016 7:51:02 AMPPASS
Inspection requested via web by Dustin Kuester t/s o/h n ok