FIR15-00822
| INSP-Sprinkler Rough-in | 5/3/2016 | 5/3/2016 | 5/3/2016 2:35:00 PM | P | PASS |
|
|
See the city approved plans for new area where the piping is ok to cover clouded and marked with todays date.
|
FIR15-00905
| INSP-Final Inspection | 5/3/2016 | 5/3/2016 | 5/3/2016 1:57:43 PM | P | PASS |
|
|
Permit finaled
|
BLD15-03303
| FIRE-Final Inspection | 5/3/2016 | 5/3/2016 | 5/3/2016 1:27:22 PM | P | FAIL |
|
|
Provide sticker at the main exit, provide single action hardware and the inner door, provide fire extinguisher as discussed. I let tenant know that the building inspector may require the interior doors hardware to meet ADA including the pocket doors.
|
FIR16-00131
| INSP-Sprinkler Rough-in | 5/3/2016 | 5/3/2016 | 5/3/2016 11:52:26 AM | P | PASS |
|
|
Pendant added in restroom. Piping is ok to cover
|
BLD16-01412
| FIRE-Final Inspection | 5/2/2016 | 5/3/2016 | 5/3/2016 9:44:19 AM | A | FAIL |
|
|
See the city approved plans for door hardware corrections needed. All other items appear ok.
|
BLD15-04525
| FIRE-Final Inspection | 5/2/2016 | 5/3/2016 | 5/3/2016 8:50:28 AM | A | PASS |
|
|
Life safety passed. The project super and I discussed adhering to the Fire Dept requirements for impaired systems.
|
FIR15-00812
| INSP-Sprinkler Rough-in | 5/2/2016 | 5/3/2016 | 5/3/2016 8:49:39 AM | A | PART |
|
|
Todays inspectio was for a general rough-in of pipe size, hangers and sprinkler spacing. See the city approved plans for corrections noted. Hydro and tenting not done yet.
|