BLD07-00143
| FIRE-Final Inspection | 5/28/2008 | 5/30/2008 | 5/30/2008 4:54:18 PM | A | FAIL |
|
|
The hood suppression system permit needs to be finaled. Fire extinguisher placement is acceptable. The tumblers in all of the doors had not been installed yet so door operation could not be verified. Also the exit signs and emergency lighting still needs to be verified.
|
FIR08-00308
| INSP-Final Inspection | 5/29/2008 | 5/30/2008 | 5/30/2008 4:52:04 PM | A | FAIL |
|
|
The manual pull station needs to be relocated to the exterior door as per the approved building plans. The remaining appliances need to be provided. The system needs to be retested.
|
FIR08-00076
| INSP-Final Inspection | 5/30/2008 | 5/30/2008 | 5/30/2008 4:50:47 PM | P | PASS |
|
|
Permit finaled
|
BLD08-01165
| FIRE-Final Inspection | 5/30/2008 | 5/30/2008 | 5/30/2008 3:31:10 PM | P | FAIL |
|
|
Relocate the fire extinguisher to meet the 75' travel distance and provide an inspection tag. Provide annual inspection for the existing fire sprinkler system. Repair the exit signs and emergency lights.
|
FIR08-00045
| INSP-Sprinkler Rough-in | 5/30/2008 | 5/30/2008 | 5/30/2008 3:29:57 PM | P | PART |
|
|
This inspection was for the installation of the 4" PIV. The PIV can be covered. I let the contractor know that it would be a good idea to get the conduit for the tamper switch installed prior to bury.
|
FIR08-00288
| INSP-Sprinkler Rough-in | 5/29/2008 | 5/30/2008 | 5/30/2008 2:11:17 PM | A | PART |
|
|
the underground flush passed. There is sprinkler blockage in the mater bathroom at the tub/shower enclosure and cpvc piping is exposed at the riser. A tenting inspection will be required as well as an inspection to see the insulation.
|
FIR08-00303
| INSP-Sprinkler Rough-in | 5/29/2008 | 5/30/2008 | 5/30/2008 1:29:27 PM | A | PART |
|
|
This inspection was for a first floor rough-in. The sprinkler piping can not be covered yet since final locations for the pendants is not done. No t-bar has been installed yet. The rough-in for the most part is ok. Two items have been noted. They include most of the branchline hangers to the north of the 3" main have been attached to the bottom of the beams. I referenced note #50 which does not allow this. Also the sidewall head installed at the top of the elevator shaft has not been installed in the 4" to 6" window.
|
FIR07-00902
| INSP-Sprinkler Rough-in | 5/29/2008 | 5/30/2008 | 5/30/2008 1:28:57 PM | A | PART |
|
|
This inspection was for a first floor rough-in. The sprinkler piping can not be covered yet since final locations for the pendants is not done. No t-bar has been installed yet. The rough-in for the most part is ok. Two items have been noted. They include most of the branchline hangers to the north of the 3" main have been attached to the bottom of the beams. I referenced note #50 which does not allow this. Also the sidewall head installed at the top of the elevator shaft has not been installed in the 4" to 6" window.
|
FIR06-00011
| INSP-Final Inspection | 5/28/2008 | 5/30/2008 | 5/30/2008 12:33:13 PM | A | PASS |
|
|
Permit finaled
|
BLD08-01079
| FIRE-Final Inspection | 5/28/2008 | 5/30/2008 | 5/30/2008 12:32:40 PM | A | PART |
|
|
A temporary occupancy was given until approved hardware is installed on the exterior exit door as discussed.
|
FIR07-01050
| INSP-Final Inspection | 5/29/2008 | 5/30/2008 | 5/30/2008 10:26:13 AM | A | PASS |
|
|
Permit finaled
|
FIR07-00874
| INSP-Sprinkler Rough-in/Hydro | 5/28/2008 | 5/30/2008 | 5/30/2008 7:55:09 AM | A | PART |
|
|
The 24 hour air test on the ALF passed but it failed on the Nurses Station.
|