Inspections for the day of: Wednesday, May 31, 2017.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE16-04108 Final5/30/20175/31/20175/31/2017 3:47:24 PMPFAIL
Final Inspection for Gatehouse
Contact Dan Hutchinson
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek
BCC 4-05-32 Code violations not to be retained. While residing existing portion conduit supports removed. All MC shall be protected from physical damage and supported as per NEC.
210.8- GFCI protection for drinking fountain shall be installed at a readily accessible location.
210.63- Service receptacles shall be installed with in 25' of AC equpment.
210.64- Service receptacle shall be installed with in 50' of electric service.
IBC- Emergency egress lighting providing 1 ft/candle of light shall be provided at exterior of each exit.
ELE17-01516 Final5/30/20175/31/20175/31/2017 1:08:20 PMAFAIL
Code 12345 Phone #: ###-#### Inspection requested via web by Dean Gernaat

Seperated flex is 24 volt fire alarm system being removed and replaced at time of inspection.
300.11- Wiring located in cavity above grid shall not be supported by or secured to ceiling system. West side is new and shall comply with present code, east existing OK to remain.
ELE16-04132 Final5/30/20175/31/20175/31/2017 12:02:23 PMAPASS
Justin Hamby Phone #: ###-#### Inspection requested via web by Laurie Hoelscher Final ok
ELE16-04132 Electrical Rough-In5/31/20175/31/20175/31/2017 12:02:08 PMPPASS
Justin Hamby Phone #: ###-#### Inspection requ
Liting and disconnecting means confirmed. Rough in ok
ELE17-00116 Electrical Rough-In5/31/20175/31/20175/31/2017 12:00:58 PMAPASS
Ceiling inspection on level 3
Contact Jon Novak
Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek
Grid complete for phase 2. Rough in ok cover
ELE17-00852 Electrical Rough-In5/31/20175/31/20175/31/2017 9:33:21 AMAPASS
Call Chris for inspection of hard lids on 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
1st floor bathroom soffit, 2nd floor hall, bath foyer soffit and bath soffit. Soffits and hardlid rough in ok cover
ELE17-00554 Electrical Rough-In5/30/20175/31/20175/31/2017 8:54:04 AMAPASS
Master tile floor heat Phone #: ###-#### Inspection requested via web by danny perrine Floor heat rough in ok cover