Inspections for the day of: Wednesday, May 31, 2017.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorScott Arellano
TitleFIRE PLAN REVIEWER
Phone #208-608-7109
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR17-00222 INSP-Final Inspection5/30/20175/31/20175/31/2017 2:10:28 PMPPASS
Testing and Inspection passed.
BLD17-00309 FIRE-Final Inspection5/31/20175/31/20175/31/2017 1:35:33 PMPPASS
Inspection Passed
FIR16-00705 INSP-Sprinkler Rough-in/Hydro5/30/20175/31/20175/31/2017 1:05:09 PMAPASS
Hydr test on 2 systems OK.
BLD16-04170 FIRE-Final Inspection5/30/20175/31/20175/31/2017 10:52:00 AMAPEND
Need fire extinguisher to be installed. Will check back later today. Larren Phone #: ###-####
FIR16-00556 INSP-Sprinkler Rough-in5/30/20175/31/20175/31/2017 9:01:43 AMAPASS
Fire sprinkler main heat traced and will be insulated at east side unheated area, access hatch provided, monitoring module installed. Testing of module will take place at fire alarm inspection. Ok to cover.
BLD16-04350 FIRE-Final Inspection5/30/20175/31/20175/31/2017 8:15:50 AMAPART
Need to install the two new fire extinguishers at the break room and lab room. Once these are installed per plan, OK to occupy new areas.
BLD16-03558 FIRE-Final Inspection5/30/20175/31/20175/31/2017 12:00:00 AMACANC
Fire Alarm permitted work not ready. BLD life safety inspection cancelled. Larren Phone #: ###-####