Inspections for the day of: Tuesday, May 4, 2004.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD04-00747 FIRE-Final Inspection5/3/20045/4/20045/4/2004 12:00:00 AMAPASS
###-#### marcus
FIR04-00235 INSP-Sprinkler Rough-in/Hydro5/3/20045/4/20045/4/2004 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 5/3/2004 at 1:18:01 PM. Contact: ###-####. The UG main actually runs to the east as shown plans; the new PIV was installed north of the sidewalk, not on the south side as shown on plans; the UG main is four inch and according to Sam of TVFP the main is reduced at an unknown location to three inch where it entrers the basement to the riser 5/4/2004 1:11:28 PM
BLD03-01252 FIRE-Final Inspection5/4/20045/4/20045/4/2004 12:00:00 AMPPASS
Adam; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
FIR03-00477 INSP-Final Inspection5/4/20045/4/20045/4/2004 12:00:00 AMPFAIL
FDC needs sign for "Basement Only" as this is a partial system 5/4/2004 2:02:33 PM