PLM09-00638
| Water and/or Sewer | 5/1/2009 | 5/4/2009 | 5/4/2009 4:14:17 PM | P | CANC |
|
|
Scheduling a Directional Drill unit and Monday afternoon looks good to them. I wanted to make sure an inspector was invited to see this portion of the project. There will be a minimal amount of trenching that will be done after the drill rig is out. Thank You, Jeff Kinney Phone #: ###-#### Internet Inspection Request from: Jeff Kinney
|
PLM09-00569
| Plumbing Rough-in | 5/4/2009 | 5/4/2009 | 5/4/2009 2:00:23 PM | P | PASS |
|
|
partial r/i -- Sam Phone #: ###-####
|
ESC08-00866
| Random Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 12:00:43 PM | A | PASS |
|
|
|
PLM08-02751
| Final | 5/4/2009 | 5/4/2009 | 5/4/2009 11:59:59 AM | A | PASS |
|
|
|
ESC08-00927
| Random Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 11:19:12 AM | A | PASS |
|
|
site ok.......ds
|
ESC07-01487
| Random Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 10:34:01 AM | A | PASS |
|
|
clean site
|
ESC08-00073
| Random Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 10:22:43 AM | A | PASS |
|
|
|
PLM09-00361
| Final | 5/1/2009 | 5/4/2009 | 5/4/2009 10:01:08 AM | A | PASS |
|
|
On site contact is Corry @ ###-#### Phone #: ###-#### Internet Inspection Request from: Jane Amy
|
PLM09-00041
| PLM-Aging Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 9:24:05 AM | | NR |
|
|
wip
|
PLM09-00040
| PLM-Aging Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 9:23:43 AM | | NR |
|
|
wip
|
PLM09-00039
| PLM-Aging Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 9:13:52 AM | | NR |
|
|
wip
|