FIR04-00349
| INSP-Conference | 4/30/2009 | 4/30/2009 | | P | |
|
|
Jeff; Phone ###-####
|
FIR09-00060
| FIR-Aging Inspection | 5/4/2009 | 5/4/2009 | 5/7/2009 3:42:04 PM | | NR |
|
|
Work in progress per Charlie Bayne. He stated work to be completed by the end of this month.
|
FIR09-00247
| INSP-Sprinkler Rough-in | 5/4/2009 | 5/4/2009 | 5/4/2009 3:49:03 PM | P | PART |
|
|
The rough-in inspection for the piping below the mezzanine passed. An additional inspection will be required when the ceilings and light fixtures have been installed.
|
BLD09-00106
| FIRE-Final Inspection | 5/4/2009 | 5/4/2009 | 5/4/2009 1:03:13 PM | P | PASS |
|
|
life safety passed
|
FIR07-00086
| INSP-Sprinkler Rough-in/Hydro | 5/4/2009 | 5/4/2009 | 5/4/2009 9:13:15 AM | A | FAIL |
|
|
I repeadedly tried to contact don by phone and I also wandered the ground and the basement floors looking for the project site.
|