FIR17-00132
| INSP-Final Inspection | 5/4/2017 | 5/4/2017 | 5/5/2017 9:42:01 AM | P | PASS |
|
|
permit finaled
|
BLD16-03176
| FIRE-Final Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 2:36:18 PM | P | FAIL |
|
|
Provide new exit signs as per plan, relocate exit signs as discussed to match plans, repair emergency lights, provide correct hardware in game room, provide plan modification addressing actual room use as discussed, provide annual inspection for the fire sprinkler system matt Phone #: ###-####
|
BLD16-02948
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:31:49 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02954
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:31:20 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02952
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:30:46 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02951
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:30:15 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02950
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:29:44 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02949
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 2:29:02 PM | A | PART |
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
BLD16-02953
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 1:56:23 PM | A | FAIL |
|
|
Need building number, need exit signs, emergency lights, exit discharge lights
|
FIR17-00107
| INSP-Sprinkler Rough-in | 5/3/2017 | 5/4/2017 | 5/4/2017 10:58:34 AM | A | PASS |
|
|
Todays inspection was for the 5' stub out only which is approved for cover
|
FIR17-00002
| INSP-Sprinkler Rough-in | 5/3/2017 | 5/4/2017 | 5/4/2017 10:31:46 AM | A | PASS |
|
|
Previous corrections have been made except the revised plans do not show the two new heads that may need to be included in the Remote Area 1 calcs. Also many of the pendant heads in the office area are now uprights. Please forward this information to the plan reviewer. All other corrections have been made and rough-in is passed.
|
BLD17-01174
| FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 8:35:17 AM | A | PASS |
|
|
life safety passed
|
FIR17-00074
| INSP-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 8:34:37 AM | A | PASS |
|
|
permit finaled
|