Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-00182 BLD-Aging Inspection5/5/20055/5/20055/6/2005 10:38:54 AMPNR
I spoke to Paul Marcolina about status. He was going to find out why sprinkler permit and life safety had not been finaled yet.
FIR04-00750 FIR-Aging Inspection5/5/20055/5/20055/6/2005 10:19:39 AM NR
work in progress
BLD05-00368 FIRE-Final Inspection5/4/20055/5/20055/5/2005 4:10:41 PMPCANC
###-#### shane Per Bill Alexander, this permit can be finaled when construction under the other building permit has started.
FIR05-00112 INSP-Sprinkler Rough-in/Hydro5/4/20055/5/20055/5/2005 4:10:38 PMPCANC
The fdc wasn't included in the hydro test. Mike said he would change that and call it in for tomorrow
FIR04-00768 INSP-Alarm Testing5/4/20055/5/20055/5/2005 4:10:36 PMAPART
Tested initiating devices on the first floor. This includes smokes, pulls and sprinkler devices. Need to test heat detectors, verify ceiling a/v's are listed for ceiling, add a/v in the electrical room and get the addresses straightened out.
FIR05-00235 INSP-Final Inspection5/5/20055/5/20055/5/2005 10:59:36 AMPPASS
Fire sprinkler passed
FIR05-00067 INSP-Final Inspection5/4/20055/5/20055/5/2005 10:31:16 AMAPASS
fire sprinkler passed
FIR04-00737 INSP-Sprinkler Rough-in5/4/20055/5/20055/4/2005 1:36:35 PMAFAIL
Inspection was for the area under the mezzanine as shown on the resubmitted plans. Plans do not show the upright heads for the combustible concealed space. There are six uprights mounted above the pendants. They are 200 degree QR brass uprights.