FIR06-00261
| INSP-Final Inspection | 5/4/2006 | 5/5/2006 | 5/7/2006 3:25:59 PM | P | FAIL |
|
|
The contractor has failed to request a rough-in inspection prior to ceiling cover. No inspection performed as the drop in tile must be removed to expose the installation for proper inspection. Noted shadowing at one location and missing drop ceiling at a closet with pendent sprinkler.
|
BLD06-00094
| FIRE-Final Inspection | 5/5/2006 | 5/5/2006 | 5/7/2006 3:19:55 PM | P | FAIL |
|
|
The project related fire sprinkler permit must be finaled before life safety building final approval. NOTE: the tenant has moved in prior to approval, notified the general contractor there will be no occupancy allowed prior to issuance of a certificate of occupancy.
|
BLD06-00667
| FIRE-Sprinkler Rough-in | 5/5/2006 | 5/5/2006 | 5/7/2006 3:08:02 PM | P | CANC |
|
|
No time to complete inspection, to be rescheduled per conversation with contractor.
|
FIR06-00296
| INSP-Sprinkler Rough-in | 5/5/2006 | 5/5/2006 | 5/7/2006 3:06:54 PM | P | CANC |
|
|
No time to complete inspection, to be rescheduled per conversation with contractor.
|
FIR05-00309
| FIR-Aging Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 2:42:56 PM | | PASS |
|
|
Field inspection of project related overhead fire sprinkler has been approved, permit passed inspection, is okay for final.
|
FIR06-00306
| INSP-Final Inspection | 5/3/2006 | 5/5/2006 | 5/5/2006 2:27:18 PM | A | PASS |
|
|
Fire alarm passed inspection, permit finaled.
|
FIR06-00280
| INSP-Final Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 2:26:35 PM | P | PART |
|
|
Fire alarm passed field inspection, final pending resubmittals for changed devices, modifications are clouded on the plan, EOL voltage field measured at 24.81.
|
FIR05-00719
| INSP-Sprinkler Rough-in/Hydro | 5/5/2006 | 5/5/2006 | 5/5/2006 12:54:28 PM | P | PASS |
|
|
Fire sprinkler corrections have been made, inspection passed.
|
FIR06-00289
| INSP-Final Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 12:53:08 PM | P | PASS |
|
|
Fire sprinkler work passed inspection, one missing 2nd pc. 401 canopy installed while on site.
|
BLD05-02218
| FIRE-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 10:48:28 AM | A | FAIL |
|
|
The project related alarm must be approved prior to life safety final inspection approval.
|
FIR06-00245
| INSP-Alarm Testing | 5/4/2006 | 5/5/2006 | 5/5/2006 10:47:28 AM | A | FAIL |
|
|
Two HVAC units not functional to enable testing, need to provide an updated map at the panel showing new monitor points, provide as builts reflecting field changes for EOL and device addresses, provide date on NAC batteries. Two pull stations, one duct detector and a/v notification devices tested okay.
|
BLD06-00325
| FIRE-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 9:55:10 AM | A | FAIL |
|
|
Need to provide suite address as indicated on review notes, need to verify path of egress lighting is installed and functional within the TI space.
|
FIR06-00284
| INSP-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 9:53:39 AM | A | PASS |
|
|
Final fire sprinkler inspection passed, permit finaled.
|
BLD05-03448
| FIRE-Conference | 5/4/2006 | 5/5/2006 | 5/5/2006 9:30:25 AM | A | PART |
|
|
Some items on correction notice have been completed including door hardware, fire ext., occupant load sign, fire sprinkler. Need to provide directional arrow at the exit sign adjacent to the SW exit stairs, remove clasp for surface lock at the pantry, provide occupant load sign in the meeting room. Still need to verify emergency lighting and exit sign illumination for the path of egress, and door lock dropout upon fire alarm activation.
|
FIR06-00164
| INSP-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 9:24:46 AM | A | PART |
|
|
Overhead sprinkler piping is good for cover at all areas, tape and paper at one ssu removed while on site, need to install ceiling tile and all escutcheons prior to final for this permit.
|
FIR05-00838
| INSP-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 9:21:57 AM | A | PASS |
|
|
Fire sprinkler work has been completed satisfactory, permit finaled.
|
FIR06-00235
| INSP-Final Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 7:43:09 AM | P | CANC |
|
|
Please call 30 minutes prior to arrival; thanks.; Phone #: ###-#### Internet Inspection Request from: Rick Jackson Inspection cancelled from web by: Rick Jackson
|
FIR06-00288
| INSP-Final Inspection | 5/4/2006 | 5/5/2006 | 5/5/2006 12:00:00 AM | A | CANC |
|
|
ROD; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|