Inspections for the day of: Tuesday, May 5, 2015.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-00788 BLD-Framing/Rough-in5/4/20155/5/20155/5/2015 3:56:22 PMAPART
This project is in phases. This would be for small office/ break room for phase 1. Darius Saxton Phone #: ###-#### Inspection requested via web by Brad Turk. Interior steel stud framed walls for phase 1 work. Noted that an interior 5" x 5" tube steel coulmn has been found that was not noted on plans, architect to provide a listed assembly for colomn. Aslo noted at radiology room remodel that interior portion of existing corridor is not maintained. Addtional 5/8" type rock will need o be installed.
BLD14-02632 BLD-Foundation5/5/20155/5/20155/5/2015 3:49:02 PMPPASS
Tom-rebar Phone #: ###-####. Column footings for new signs westside of building C.
BLD14-02632 BLD-Footing5/5/20155/5/20155/5/2015 3:39:57 PMPCANC
rebar Phone #: ###-####
BLD13-03600 BLD-Wall Bracing5/5/20155/5/20155/5/2015 3:38:55 PMPPASS
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD13-03582 BLD-Wall Bracing5/5/20155/5/20155/5/2015 3:25:03 PMPPASS
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD13-03583 BLD-Wall Bracing5/5/20155/5/20155/5/2015 2:51:58 PMPPASS
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD13-03590 BLD-Framing/Rough-in5/5/20155/5/20155/5/2015 2:49:04 PMPNR
rough frame inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson. Needs fire sprinkler rough in inspection.
BLD13-03579 BLD-Wall Bracing5/5/20155/5/20155/5/2015 1:55:38 PMPPASS
2nd floor intershear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD14-03466 BLD-Final5/4/20155/5/20155/5/2015 1:33:09 PMPDONE
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
BLD14-03466 DOC - Permit Finaled5/5/20155/5/20155/5/2015 1:32:47 PMPPASS
BLD15-00897 BLD-Wall Bracing5/4/20155/5/20155/5/2015 1:31:38 PMPPASS
Shear // Brett Phone #: ###-####
BLD15-00172 BLD-Final5/4/20155/5/20155/5/2015 1:31:01 PMAPASS
Brett Phone #: ###-####
BLD15-00172 DOC - Permit Finaled5/5/20155/5/20155/5/2015 1:30:37 PMPPASS
BLD15-01104 BLD-Foundation5/5/20155/5/20155/5/2015 12:45:20 PMANR
Mark - ###-####-foundation rebar. Needs elec. rough in.
GCB15-00004 GCB-Final5/4/20155/5/20155/5/2015 11:39:32 AMAPASS
Brandon ###-####. All issues resolved.
BLD14-03466 BLD-Conference5/4/20155/5/20155/4/2015 3:43:05 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher Inspection cancelled from web by: Laurie Hoelscher