FIR05-00223
| INSP-Final Inspection | 5/6/2005 | 5/6/2005 | 5/6/2005 3:15:02 PM | P | PASS |
|
|
Fire sprinkler finaled
|
FIR04-00768
| INSP-Alarm Testing | 5/5/2005 | 5/6/2005 | 5/6/2005 2:17:17 PM | A | PART |
|
|
Contact: ###-####. See approved plans, sheet 1 for items left to verify.
|
FIR04-00737
| INSP-Sprinkler Rough-in | 5/6/2005 | 5/6/2005 | 5/6/2005 1:47:00 PM | P | PART |
|
|
Sprinkler piping under mezzanine, including the ramp are ok to cover. Flexible cplg has been installed on rise up.
|
FIR05-00112
| INSP-Sprinkler Rough-in/Hydro | 5/5/2005 | 5/6/2005 | 5/6/2005 12:04:01 PM | A | PART |
|
|
Above ground hydro test passed
|
MIS05-00048
| FIR-Final | 5/5/2005 | 5/6/2005 | 5/6/2005 10:11:09 AM | A | PASS |
|
|
Fire life safety finaled
|