FIR08-00093
| FIR-Aging Inspection | 5/6/2008 | 5/6/2008 | 5/8/2008 3:48:12 PM | | NR |
|
|
work is in progress
|
FIR07-00863
| INSP-Sprinkler Rough-in/Hydro | 5/5/2008 | 5/6/2008 | 5/6/2008 4:02:02 PM | A | PART |
|
|
First floor wet system and second floor anti-freeze system hydro tests passed. First floor sprinkler piping rough-in is passed and the piping can be covered. See the city approved plans for the location of one pendant that needs relocated and one pendant that needs to be added on the first floor. The second floor anti-freeze piping does not quite match the plans. Mike is going to have a set of as-builts made with modified hydraulic calculations for the next inspection.
|
FIR08-00212
| INSP-Sprinkler Rough-in/Hydro | 5/5/2008 | 5/6/2008 | 5/6/2008 3:27:02 PM | A | PART |
|
|
See the city approved plans for rooms marked in red with "OK" that can have the piping covered. The rooms with out the "OK" either had defieciencies or did not have completed work and can not be covered. No sprinkler contractor was on site.
|
FIR08-00036
| INSP-Sprinkler Rough-in/Hydro | 5/2/2008 | 5/6/2008 | 5/6/2008 3:25:13 PM | A | PASS |
|
|
Above ground hydro test passed.
|
FIR05-00863
| INSP-Final Inspection | 5/5/2008 | 5/6/2008 | 5/6/2008 2:31:16 PM | A | PASS |
|
|
Permit finaled
|