Inspections for the day of: Tuesday, May 6, 2014.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC12-00364 General Inspection5/5/20145/6/20145/6/2014 4:31:38 PMAPASS
WIP. Exisiting vegetation at lot provides buffer from disturbance. Mainly interior work remaining. No corrections at this time.
ESC13-00520 General Inspection5/6/20145/6/20145/6/2014 3:34:21 PM PASS
ESC13-01040 General Inspection5/6/20145/6/20145/6/2014 11:25:01 AM PASS
Roofers and framers on site. Contractors staying off open areas. No violations observed.
ESC13-00144 General Inspection5/6/20145/6/20145/6/2014 11:01:55 AM PASS
No changes or construction acitivity. River rock and dirts stockpiles are still on site. Though no vegetation on future road site above trunk line, there does not seem to be any dust generated on this windy day. Will continue to monitor.
ESC13-00755 General Inspection5/6/20145/6/20145/6/2014 10:47:36 AMPPASS
Follow up inspection to see if action items from the 5/1 conference were completed.

Both entrances have new rock that is also extended. Very little sediment accumulation in gutters along Lysted. West entrance on Council Springs does not have any significant track out.

Site conditions are much improved. Need to check if DI on north side of Warm Springs between Council Springs and Eckert. Lots of sediment in gutters, unclear if it is from Terraces project trackout in preveious weeks - numerous projects are in the vicinity. Will follow up. No corrections at this time.
ESC13-00975 General Inspection5/6/20145/6/20145/6/2014 10:35:50 AM PASS
No discharges or sediment runoff to the stormwater swales. Swales have ring of grassy vegetation around the infiltration rocks. Workers onsite. No corrections at this time.
ESC13-00951 General Inspection5/6/20145/6/20145/6/2014 10:34:21 AM PASS
No activity at time of inspection. Frame of townhome is erected, but interior work remains. Millet access road is clean.
ESC13-00684 General Inspection5/6/20145/6/20145/6/2014 10:18:28 AM PASS
Installing curb along side Warm Springs. Large lined washout pit is provided on the upper staging area for the work. Road into development has been compacted, looks like it will soon be paved. Site has good vegetative and structural buffer. No corrections at this time.
ESC14-00341 Site Preparation5/5/20145/6/20145/6/2014 10:04:41 AMAPASS
John Phone #: ###-####

Permit posted. Excavation is downslope from the Boise City Canal, which is lined with stone bricks and and also a landscaped buffer. GC Jon King explained the scope of project. Will use small tractor to haul dirt down from top of driveway at Warm Springs. Approved for construction.
ESC13-00854 General Inspection5/6/20145/6/20145/6/2014 9:04:35 AM PASS
No construction or disturbance at site. Will check with Knife River to see if project is complete. No activity on attached BLD permit.
ESC13-00655 General Inspection5/6/20145/6/20145/6/2014 8:44:45 AM PASS