Inspections for the day of: Wednesday, May 6, 2015.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00529 INSP-Final Inspection5/5/20155/6/20155/6/2015 5:37:25 PMPFAIL
Flow test requirements were not met for riser 4, requires acceleration device. Water flow timed at 66 seconds, requirement for 4 outlet manifold is 40 seconds. Riser 3 passed with 37 second flow.
FIR15-00301 INSP-Final Inspection5/5/20155/6/20155/6/2015 5:35:52 PMPPART
Partial final pass. Functional alarm test complete with the exception of flow switches on risers 1 & 2. Prior to final the following items to be completed: provide updated plans, provide knox box, provide document box, "Fire Alarm Control Panel" signage on doors, floor plan with initiating devices posted at FACP, and repaint alarm bell and add call 911 when sounding verbage.
BLD15-00113 FIRE-Final Inspection5/5/20155/6/20155/6/2015 5:23:31 PMPPASS
Fire life safety pass
FIR15-00107 INSP-Sprinkler Rough-in/Hydro5/5/20155/6/20155/6/2015 4:01:22 PMAPASS
Sprinkler system addition from 4" main to new bays was isolated and hydrostatic test passed. Rough-in complete.

Field verified appropriate use of 12 high temperature heads within 7' of radiant heaters.

Changes in field were made, resubmittal is under review. Per phone call with Tim Frost, storage room ok.
FIR15-00154 INSP-Final Inspection5/6/20155/6/20155/6/2015 3:34:59 PMPPASS
Scope of work complete. Permit finaled.
BLD11-00961 FIRE-Final Inspection5/5/20155/6/20155/6/2015 2:05:59 PMAPASS
Fire life safety pass. Aging permit; inspection completed in line with BLD 15-00889 inspection.
BLD14-02471 FIRE-Conference5/5/20155/6/20155/6/2015 12:50:58 PMADONE
Walk through with Mike. Discussed life safety items to include exit signs, door hardware, fire extinguishers. Also discussed need for sprinkler underground flush, rough-in and hydrostatic test inspections.
FIR15-00082 INSP-Sprinkler Rough-in/Hydro5/5/20155/6/20155/6/2015 10:49:43 AMAPASS
1st floor hydrostatic test passed.