Inspections for the day of: Monday, May 6, 2019.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE16-01940 ELE-Aging Inspection5/6/20195/6/20195/7/2019 9:13:18 AM PASS
Ok final.
ELE19-01493 Electrical Rough-In5/6/20195/6/20195/6/2019 2:18:16 PMPPASS
please call when entering whitewater park underground inspection area is across Quinn''s pond Phone #: ###-#### Inspection requested via web by Tye Thomas Ok cover conduit S side of Whitewater for aeration pumps for Quinns pond.
ELE18-01606 Electrical Rough-In5/5/20195/6/20195/6/2019 2:05:07 PMPPASS
Building B
C Units
Drop lid 2nd, 3rd and 4th Floor Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover areas listed.
ELE19-01543 Final5/2/20195/6/20195/6/2019 1:39:49 PMPPASS
Can meet you please call ahead with as much notice as possible. Have a Great day Phone #: ###-#### Inspection requested via web by TRENT Swaim Ok final
ELE19-00584 Electrical Rough-In5/6/20195/6/20195/6/2019 12:07:53 PMPPASS
Contact: Derrick Kamper... ceiling inspection and partial final in suite 75 please Phone #: ###-#### Inspection requested via web by Deb Gooden Ok cover ceiling in area 50 lower plaza. Partial final for area 78 storage room lower plaza. Final will be given when area 50 is completed.
ELE19-01581 Temporary Service5/6/20195/6/20195/6/2019 11:28:31 AMPPASS
Please call Mike Brown ###-#### w/any questions Phone #: ###-#### Inspection requested via web by Bonnie Page t/s u/g n ok
ELE17-03370 Final5/2/20195/6/20195/6/2019 10:50:33 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok final.
ELE19-01505 Final5/3/20195/6/20195/6/2019 10:12:24 AMANR
Key is in backyard under flower pot by fertilizer Phone #: ###-#### Inspection requested via web by Same Electric Talked to Chris about another permit to be pulled for lower apartment kitchen area. Cabinets are being installed, and there is open wiring in ceiling and 1 wall area. Either Same Day pulls another permit, or another Elec Contractor before I can final this permit out. Please call back in when permit completed.
ELE18-02184 Final5/3/20195/6/20195/6/2019 9:45:16 AMPCANC
Electrical final. Jason is the contact. Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
ELE19-01486 Final5/3/20195/6/20195/6/2019 9:26:35 AMAPASS
Owner is notified that someone has to be on site for inspection Phone #: ###-#### Inspection requested via web by Winters LLC Ok final. 1-20a and 1-30a circuit to power small 1 car garage. Exterior panel on garage has GEC established.
ELE19-01530 Final5/4/20195/6/20195/6/2019 8:59:50 AMANH
Please call electrician, Preston Saey with any questions: ###-#### Inspection requested via web by Rob Maes Knocked no answer. Mentioned to installer on RI that someone had to be present. Gate was open on left side. City ordinance doesnt allow us to access property unless someone is present.
ELE19-00911 Final5/2/20195/6/20195/3/2019 2:15:02 PMACANC
Final Trim Inspection Phone #: ###-#### >> Inspection requested via web by Same Electric Inspection cancelled from web by: Same Electric