FIR01-00104
| INSP-Sprinkler Rough-in/Hydro | 5/4/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | A | PART |
|
|
###-#### OK to cover under slab mains 5/7/2001 10:37:30 AM
|
FIR01-00162
| INSP-Final Inspection | 5/4/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | P | FAIL |
|
|
Dick ###-#### Reinsp Fail All items on C/N completed 5/7/2001 3:30:45 PM
|
BLD01-00978
| FIRE-Final Inspection | 5/7/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | P | PASS |
|
|
Shane ###-#### Final Ok for certificate of completion 5/7/2001 3:57:58 PM
|
BLD01-00142
| FIRE-Final Inspection | 5/7/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 05/07/2001 at 10:33:23. Contact: ###-####. Final Fail Approved plans not on site 5/7/2001 3:32:40 PM
|
BLD01-01062
| FIRE-Final Inspection | 5/7/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | P | PASS |
|
|
john ###-#### Final OK for certificate of occupancy 5/7/2001 5:02:52 PM
|
FIR01-00162
| INSP-Alarm Testing | 5/7/2001 | 5/7/2001 | 5/7/2001 12:00:00 AM | P | FAIL |
|
|
Added by Inspector: 406 On 5/7/2001 3:31:59 PM Final Fail Incorrect battery size
|