FIR01-00613
| INSP-Final Inspection | 5/2/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | A | FAIL |
|
|
Duct smoke detector in Jo anns did not work properly and signals at the monitoring company dont match. All inspections to be called back in for friday morning 5/7/2003 9:23:09 AM
|
BLD02-02888
| FIRE-Conference | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | A | PASS |
|
|
Fire life safety finaled 5/7/2003 12:43:55 PM
|
FIR03-00118
| INSP-Sprinkler Rough-in/Hydro | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | A | FAIL |
|
|
No approved plans on site. No inspection done. I requested that the contractor not cover anything up. 5/7/2003 9:48:07 AM
|
BLD02-02785
| FIRE-Final Inspection | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | A | FAIL |
|
|
###-#### Need to test duct smoke detector 5/7/2003 1:18:25 PM
|
BLD01-02497
| BLD-Conference | 5/7/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | PASS |
|
|
Fire life safety finaled. Reference FIR02-00202 and FIR02-00327 5/8/2003 12:18:33 PM
|
FIR02-00423
| INSP-Sprinkler Rough-in/Hydro | 5/7/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | PART |
|
|
Started the 24 hour test on the dry system at 1:30. Guage is at 45 psi
|
FIR03-00188
| INSP-Final Inspection | 5/7/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | PASS |
|
|
Hood suppresion system operated correctly
|
FIR02-00473
| INSP-Final Inspection | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | PASS |
|
|
Fire sprinklers finaled 5/7/2003 2:21:34 PM
|
BLD03-00301
| FIRE-Final Inspection | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | FAIL |
|
|
Could not connect the hood system to the fire alarm because fire alarm system is not complete yet. Painted sprinkler heads and canopies through out tenant space. Provide approved door hardware on the office door in kitchen area 5/7/2003 3:47:19 PM
|
FIR03-00030
| INSP-Final Inspection | 5/6/2003 | 5/7/2003 | 5/7/2003 12:00:00 AM | P | PASS |
|
|
|