Inspections for the day of: Wednesday, May 7, 2008.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00238 INSP-Final Inspection5/6/20085/7/20085/8/2008 10:32:10 AMPPART
Final pending accurate riser diagram for field changes in circut connections and modified plans indicating omission of work shown for the conference room area not to be completed at this time per contractor. Functional testing for the K-9 office and kennel room alarm notification devices passed.
BLD08-00206 FIRE-Final Inspection5/7/20085/7/20085/7/2008 3:10:25 PMPPASS
C/N items verified, inspection passed.
BLD08-00342 FIRE-Final Inspection5/7/20085/7/20085/7/2008 2:32:04 PMPFAIL
Building modifications have disrupted existing fire sprinkler system coverage. A fire sprinkler permit will be required to complete the necessary corrections.
BLD08-00574 FIRE-Final Inspection5/6/20085/7/20085/7/2008 1:54:23 PMANH
Door locked, no access to complete inspection.
BLD08-00573 FIRE-Final Inspection5/6/20085/7/20085/7/2008 1:53:31 PMAPASS
Items on correction notice are finished, life safety passed.
FIR08-00180 INSP-Sprinkler Rough-in/Hydro5/6/20085/7/20085/7/2008 1:46:47 PMAPART
OH install at the east office area first and second floors for rooms and areas completed to date are okay for cover, no access at one hallway due to flooring work underway, missing heads at two utility rooms 2nd floor, verified corrections are finished at the entry vestibule, need access to verify coverage at the concealed combustible spaces under the stairway at two locations. Hydrostatic testing for the new 10"supply main at the warehouse completed satisfactory, also discussed seismic bracing issues.