MEC14-01748
| Final | 5/6/2014 | 5/7/2014 | 5/8/2014 12:37:24 PM | P | PASS |
|
|
Comm. business: The Melting Pot. Can meet with manager on site if needed. Please call plumber, Carl with questions ###-####. Phone #: ###-#### >> Inspection requested via web by James Staley
|
MEC14-01759
| Pressure Test | 5/7/2014 | 5/7/2014 | 5/7/2014 4:37:38 PM | P | PART |
|
|
Pressure gauge is located by gas meter (2psi system) Phone #: ###-#### >> Inspection requested via web by Travis Baker 60# test meter to rtu's and down to water heaters in basement. header at cookline not done.
|
MEC14-00451
| Final | 5/7/2014 | 5/7/2014 | 5/7/2014 4:36:35 PM | P | CANC |
|
|
Please call Ted one hour a head of time for flue test. Customer won''t be available until after 2p. M. >> Inspection requested via web by Margie Rowe they called and canceled
|
MEC12-03006
| Mec-Aging Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 2:20:37 PM | | CANC |
|
|
|
MEC10-04358
| Mec-Aging Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 2:20:24 PM | | CANC |
|
|
|
MEC11-00214
| Mec-Aging Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 2:20:14 PM | | CANC |
|
|
|
MEC11-00134
| Mec-Aging Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 2:20:04 PM | | CANC |
|
|
|
MEC11-00126
| Mec-Aging Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 2:14:05 PM | | CANC |
|
|
|
MEC11-00126
| DOC - Permit Expired | 5/7/2014 | 5/7/2014 | 5/7/2014 2:04:32 PM | P | PASS |
|
|
expire permit
|
MEC14-01679
| Rough-in | 5/7/2014 | 5/7/2014 | 5/7/2014 1:53:46 PM | P | FAIL |
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Reeves provide access to the kitchen exhaust fan, provide fresh air damper, provide automatic damper on kitchen hood makeup air
|
PLM14-01224
| Final | 5/6/2014 | 5/7/2014 | 5/7/2014 1:39:45 PM | A | PASS |
|
|
Daniel Phone #: ###-#### 100# test ok
|
MEC14-01697
| Rough-in | 5/3/2014 | 5/7/2014 | 5/7/2014 9:27:55 AM | A | PASS |
|
|
>> Inspection requested via web by Jason Robinson fp ri ok X 2
|
MEC14-01335
| Rough-in | 5/6/2014 | 5/7/2014 | 5/7/2014 9:27:20 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by GREGORY ANDERSEN ri 20# test ok X 2
|
MEC14-01696
| Rough-in | 5/3/2014 | 5/7/2014 | 5/7/2014 9:09:30 AM | A | PASS |
|
|
>> Inspection requested via web by Jason Robinson ri ok X2
|
MEC14-01723
| Final | 5/6/2014 | 5/7/2014 | 5/7/2014 8:51:20 AM | A | PASS |
|
|
This is a Flue Pressure and Final Inspect. Pls meet our installer at home at 10 am. Install Mgr, Allen, Ph is ###-####. Pls call homeowner prior to inspect at ###-#### - Holly. Phone #: ###-#### >> Inspection requested via web by Mary LaFayette
|
MEC13-04534
| Final | 5/6/2014 | 5/7/2014 | 5/7/2014 8:35:24 AM | A | PASS |
|
|
mechanical final Phone #: ###-#### >> Inspection requested via web by Joe Bertwell
|
MEC14-00246
| Rough-in | 5/6/2014 | 5/7/2014 | 5/7/2014 8:20:03 AM | A | PASS |
|
|
mike Phone #: ###-#### ri final ok with garage ceiling penatrations protected, soffit per owner
|
MEC14-00246
| Final | 5/7/2014 | 5/7/2014 | 5/7/2014 8:18:47 AM | P | PASS |
|
|
mike Phone #: ###-#### ri final ok
|
MEC14-00219
| Final | 5/6/2014 | 5/7/2014 | 5/7/2014 7:30:54 AM | A | CANC |
|
|
Please call with any questions or concerns. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy Inspection cancelled from web by: Jennifer Roy
|
MIS14-00097
| MEC-Conference | 5/6/2014 | 5/7/2014 | 5/6/2014 4:19:19 PM | P | FAIL |
|
|
complaint doing work without permit; remodel inside including elec, plm, mech. Changed utility room into bathroom and moved utility room to basement, kitchen remodel changed flat ceiling to vaulted ceiliing. Electrical concerns with grounding/safety. 1) tune up dryer vent 2) complete gas piping upgrades and test 3) install b-vent from furnace and water heater for clearances 4) check combustion air for furnace and water heater 5) permit all mechanical work
|
MIS14-00097
| PLM-Conference | 5/6/2014 | 5/7/2014 | 5/6/2014 4:16:57 PM | A | FAIL |
|
|
complaint doing work without permit; remodel inside including elec, plm, mech. Changed utility room into bathroom and moved utility room to basement, kitchen remodel changed flat ceiling to vaulted ceiliing. Electrical concerns with grounding/safety. 1) trap and vent washer box 2) vent lav behind the washer box 3)weep hole required on water heater t&p 4)install directional fitting in 3" waste line in basement ceiling by bath 5) permit allplumbing work
|