PLM02-00181
| Plumbing Rough-in | 5/7/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/07/2002 at 13:01:45. Contact: ###-####. main restroom,s on north side and janitor sink area rough-in and test ok 5/8/2002 12:15:53 PM
|
PLM02-00181
| Roof Drains | 5/7/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/07/2002 at 13:02:30. Contact: ###-####. roof drain,s on south lower roof section water test ok 5/8/2002 12:13:00 PM
|
PLM02-01204
| Water and/or Sewer | 5/7/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
RAYMOND ###-####
|
PLM02-01204
| Sprinkler (Final) | 5/7/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
RAYMOND ###-####
|
PLM01-02494
| Final | 5/7/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
fn dan- ###-####
|
PLM02-01254
| Sprinkler (Final) | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 06:30:16. Contact: ###-####. tie in ok to cover need backflow device tested and certified 5/8/2002 10:26:27 AM
|
PLM02-01254
| Water and/or Sewer | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 06:39:03. Contact: ###-####.
|
PLM02-01249
| Sprinkler (Final) | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 06:40:28. Contact: ###-####.
|
PLM02-01227
| Plumbing Rough-in | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 07:33:21. Contact: ###-####.
|
PLM02-01296
| Final | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-01298
| Final | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | P | NR |
|
|
###-#### DEBBIE
|
PLM02-00210
| Final | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 10:45:06. Contact: ###-####. premis protection need,s certified expose floor drain in shop area provide bolt,s for sump lid,s check flush valves in restroom,s may need adjustments called plumbing contractor 5/8/2002 3:08:16 PM
|
PLM02-01298
| Water and/or Sewer | 5/8/2002 | 5/8/2002 | 5/8/2002 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 360 On 5/8/2002 5:42:00 PM water line from control and drain valves to two hydrants in shop area test ok 5/8/2002 5:46:14 PM
|