Inspections for the day of: Tuesday, May 8, 2012.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR12-00118 INSP-Final Inspection5/8/20125/8/20125/9/2012 3:36:01 PMPPASS
Permit finaled
FIR12-00041 INSP-Sprinkler Rough-in/Hydro5/8/20125/8/20125/8/2012 3:34:21 PMPPASS
The overhead hydro tests passed. Visual increase in pressure over the testing time.
FIR12-00029 INSP-Alarm Testing5/7/20125/8/20125/8/2012 1:33:42 PMACANC
inspection canceled due to the fire alarm tech not showing up. No inspection was performed.
BLD11-01685 FIRE-Final Inspection5/7/20125/8/20125/8/2012 1:31:17 PMAPASS
Life safety passed
FIR11-00544 INSP-Final Inspection5/7/20125/8/20125/8/2012 7:53:33 AMAPASS
Permit finaled
FIR12-00113 INSP-Final Inspection5/7/20125/8/20125/8/2012 7:42:08 AMAFAIL
Simplex technician did not arrive at project site for inspection as scheduled. Noted seven over spaced strobes which were relocated by the electrician as Jason and I waited for Simplex. No functional testing of devices was performed.