Inspections for the day of: Friday, May 8, 2015.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00411 FIR-Aging Inspection5/8/20155/8/20155/11/2015 7:08:14 AM NR
Contractor is out of business
BLD15-01441 FIRE-Final Inspection5/8/20155/8/20155/8/2015 3:33:43 PMPPASS
life safety passed
BLD15-01411 FIRE-Final Inspection5/5/20155/8/20155/8/2015 3:28:41 PMPCANC
Overbooked and contact did not answer phone. I left a message on voice mail. Jesse Phone #: ###-####// please call before
FIR15-00256 INSP-Sprinkler Rough-in5/8/20155/8/20155/8/2015 3:18:54 PMPPASS
Underground supply piping is ok to cover
FIR15-00309 INSP-Sprinkler Rough-in5/8/20155/8/20155/8/2015 3:12:55 PMPPASS
Underground supply line is ok to cover
FIR15-00310 INSP-Sprinkler Rough-in5/8/20155/8/20155/8/2015 3:00:07 PMPPASS
Underground supply piping is ok to bury
FIR15-00173 INSP-Sprinkler Rough-in5/8/20155/8/20155/8/2015 2:53:45 PMPPASS
The modified/new soffits have been filled with insulation. Piping can be covered.
BLD15-00523 FIRE-Final Inspection5/7/20155/8/20155/8/2015 2:45:55 PMAPASS
Life safety passed
FIR14-00920 INSP-Final Inspection5/6/20155/8/20155/8/2015 2:28:59 PMPPASS
Permit finaled
FIR14-00761 INSP-Sprinkler Rough-in5/7/20155/8/20155/8/2015 2:23:31 PMAPASS
Overhead rough-in and tenting inspection passed. Piping can be covered.
BLD14-03559 FIRE-Final Inspection5/7/20155/8/20155/8/2015 1:22:08 PMAPASS
Life safety passed
FIR15-00085 INSP-Final Inspection5/7/20155/8/20155/8/2015 1:19:28 PMAPASS
Permit finaled
BLD14-01411 FIRE-Final Inspection5/7/20155/8/20155/8/2015 12:06:25 PMACANC
life safety Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
NAF15-00006 INSP-Sprinkler Rough-in/Hydro5/7/20155/8/20155/8/2015 10:14:39 AMPPASS
Overhead hydro test of the first floor passed
NAF14-00028 INSP-Sprinkler Rough-in/Hydro5/7/20155/8/20155/8/2015 10:10:53 AMPPASS
Underground hydro test passed
FIR14-00622 INSP-Final Inspection5/7/20155/8/20155/8/2015 9:59:22 AMACANC
Brandon Phone #: ###-####
FIR15-00300 INSP-Final Inspection5/7/20155/8/20155/8/2015 9:51:45 AMAPASS
permit finaled
BLD14-01409 FIRE-Final Inspection5/7/20155/8/20155/8/2015 9:34:17 AMAPASS
life safety passed
FIR15-00191 INSP-Final Inspection5/7/20155/8/20155/8/2015 9:32:44 AMAPASS
Permit finaled
FIR14-00620 INSP-Final Inspection5/7/20155/8/20155/8/2015 9:30:54 AMAPASS
Permit finaled
BLD15-00751 FIRE-Final Inspection5/7/20155/8/20155/8/2015 8:18:04 AMAPASS
Life safety passed
FIR15-00202 INSP-Final Inspection5/7/20155/8/20155/8/2015 8:16:09 AMAPASS
Permit finaled
FIR15-00086 INSP-Final Inspection5/7/20155/8/20155/8/2015 8:14:27 AMAPASS
Permit finaled