ELE18-01115
| Final | 5/8/2018 | 5/8/2018 | 5/8/2018 1:54:47 PM | P | CANC |
|
|
INSTALLED BATH FAN ONLY IN BATHROOM - ONLY Inspection requested via web by Matthew White Ok final.
|
ELE18-01725
| Temporary Service | 5/8/2018 | 5/8/2018 | 5/8/2018 1:15:11 PM | P | PASS |
|
|
temp pole at transformer Phone #: ###-#### Inspection requested via web by Dan Rohl t/s u/g n ok
|
ELE18-01701
| Electrical Rough-In | 5/7/2018 | 5/8/2018 | 5/8/2018 12:32:17 PM | A | PASS |
|
|
Installed 2 new rooftop AC units. FINAL NEEDED TOO Phone #: ###-#### Inspection requested via web by Stuart Welton Ok final. Max fuse 40 with #8 for 1 unit. Max fuse 60 with #6 for 2nd unit. All weather proof fittings.
|
ELE17-03721
| Final | 5/7/2018 | 5/8/2018 | 5/8/2018 10:19:31 AM | A | PASS |
|
|
It will be open. If you have any questions please feel free to contact Tony ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok final.
|
ELE18-01705
| Rough-In Permanent Service | 5/7/2018 | 5/8/2018 | 5/8/2018 9:45:00 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk p/s u/g n ok
|
ELE18-01704
| Rough-In Permanent Service | 5/7/2018 | 5/8/2018 | 5/8/2018 9:44:41 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk p/s u/g n ok
|
ELE18-01347
| Final | 5/7/2018 | 5/8/2018 | 5/8/2018 9:09:18 AM | A | PASS |
|
|
For access please call Jaman 1/2 hr prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Terry Scott Ok final mstr bath.
|