BLD01-02970
| FIRE-Final Inspection | 5/9/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | A | PART |
|
|
Added by Inspector: 409 On 5/9/2002 8:15:51 AM temp only per Dave Miller; second floor not complete; NW exit not ready - not used for tenent under BLD02-00570; corridor complete on first floor
|
BLD02-00570
| FIRE-Final Inspection | 5/9/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 409 On 5/9/2002 8:17:00 AM occ approved; shell not complete under BLD01-02970 and is under temp per Dave Miller
|
FIR02-00131
| INSP-Sprinkler Rough-in/Hydro | 5/7/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/07/2002 at 14:36:59. Contact: ###-####. okay to cover 5/9/2002 1:32:35 PM
|
BLD01-02222
| FIRE-Conference | 5/8/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | A | PART |
|
|
Scheduled by Inspector: 409 On 5/8/2002 3:49:48 PM met with Jim Storey and walked through the project; some dampers appear to have the motor too close to wall to have improper fire stopping where motor hits rated wall 5/9/2002 11:01:54 AM
|
BLD02-00437
| FIRE-Final Inspection | 5/9/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 05/09/2002 at 07:53:25. Contact: ###-####. okay to occupy rooms 509-529; phasing of this project is needed to complete bathrooms and hallway 5/9/2002 2:55:58 PM
|
BLD01-03156
| FIRE-Final Inspection | 5/9/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | P | FAIL |
|
|
rob ###-#### door hardware at main exit; alarms not ready; sprinkler escutcheons; FACP and sprinkler control signs on doors; 5/9/2002 4:13:59 PM
|
FIR02-00145
| INSP-Sprinkler Rough-in | 5/9/2002 | 5/9/2002 | 5/9/2002 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 409 On 5/9/2002 3:00:02 PM okay on this floor; awaiting alarms
|