Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-02696 FIRE-Final Inspection5/7/20035/9/20035/9/2003 12:00:00 AMAFAIL
bill; Phone #: ###-#### Corrections needed for the fire alarm system. See attached FIR01-00613 5/9/2003 11:23:43 AM 5/9/2003 11:24:10 AM
BLD01-03110 FIRE-Final Inspection5/7/20035/9/20035/9/2003 12:00:00 AMAPASS
Fire sprinklers finaled 5/9/2003 11:22:19 AM
BLD02-00425 FIRE-Final Inspection5/7/20035/9/20035/9/2003 12:00:00 AMAPASS
Fire life safety finaled 5/9/2003 11:21:26 AM
FIR02-00001 INSP-Final Inspection5/7/20035/9/20035/9/2003 12:00:00 AMAPASS
rick; Phone #: ###-#### Internet Inspection Request from: Darla Downs
FIR02-00316 INSP-Final Inspection5/8/20035/9/20035/9/2003 12:00:00 AMAFAIL
Strobes exceed 15' from the ends of corridors and manual pull stations exceed 5' from door in several locations. Fire alarm system had a trouble generated from somewhere on the sprinkler system. No inspection done. See approved job site plans for specific locations. All fire sprinkler monitoring devices and alarm devices need tested 5/9/2003 11:42:22 AM
FIR02-00423 INSP-Sprinkler Rough-in/Hydro5/8/20035/9/20035/9/2003 12:00:00 AMAFAIL
Can not complete the fire sprinkler inspection until the fire alarm system is ready. The fire sprinkler connections to the fire alarm system are the only items left to complete, dry pipe riser and wet riser. 5/9/2003 11:29:27 AM
FIR02-00152 INSP-Final Inspection5/9/20035/9/20035/9/2003 12:00:00 AMAPASS
FIR01-00587 INSP-Final Inspection5/9/20035/9/20035/9/2003 12:00:00 AMAPASS
FIR01-00613 INSP-Final Inspection5/9/20035/9/20035/9/2003 12:00:00 AMAFAIL
A duplex electrical outlet needs blanked off on the dedicated fire alarm circuit. Provide keys and map for the knox key box. Provide lock on dedicated circuit
FIR02-00308 INSP-Final Inspection5/9/20035/9/20035/9/2003 12:00:00 AMAPASS
BLD02-00155 BLD-Conference5/9/20035/9/20035/9/2003 12:00:00 AMADONE
I left a correction notice with construction superintendant, Mel, stating that the new addition to the church can not be occupied until all sign offs had been received and a Certificate of Occupancy is issued.
BLD03-00301 FIRE-Final Inspection5/9/20035/9/20035/9/2003 12:00:00 AMPPART
A temp occupancy was given with Dave Millers permission until the fire alarm system for the shopco plaza has been inspected and approved. Fire sprinkler is finaled. Fire alarm has a temp. Fire life safety is ok except for the office door handle is not approved type. Since the south HVAC unit did not work I had Gary, the superintendant, lock out the unit until it can be repaired and reinspected
FIR02-00432 INSP-Alarm Testing5/9/20035/9/20035/9/2003 12:00:00 AMPFAIL
North hvac unit in the Basilio's restraunt would not operate. It is locked out until it can be repaired and tested. Smoke detector over panel, battery troubles, phone lines and pull station have been tested. No other items tested. This initial test was just to get the restraunt a temp occupancy. The main inspection to be called in next week. 5/9/2003 2:47:53 PM
BLD03-00171 FIRE-Alarm Testing5/9/20035/9/20035/9/2003 12:00:00 AMPFAIL
Provide updated online to sam rogers and a map at the fire alarm panel 5/9/2003 4:01:16 PM
FIR03-00176 INSP-Sprinkler Rough-in5/9/20035/9/20035/9/2003 12:00:00 AMPFAIL
Provide insulation on cpvc piping at north end of building 5/9/2003 4:22:20 PM